Under Review |
Application and Supporting Studies |
Title | Author | Posted Date |
| Addendum report on the Application for the Wolverine Coal Project from Westerern Canadian Coal (prop) to Bob Hart (EAO) July 2004. | Western Canada Coal Corporation | 2004/07/21 |
| Volume 1. Additional Information Report - Main Document. Submitted by Western Canadian Coal (prop) to Bob Hart (EAO) on May 12/04.
Update: Section ommission 10.9.1.8 now included July 22/04. | Western Canada Coal Corporation | 2004/05/12 |
| Volume 2. Additional Information Report - Figures, Part 1. Submitted by Western Canadian Coal (prop) to Bob Hart (EAO) on May 12/04. | Western Canada Coal Corporation | 2004/05/12 |
| Volume 2 continued. Additional Information Report - Figures, Part 2. Submitted by Western Canadian Coal (prop) to Bob Hart (EAO) on May 12/04. | Western Canada Coal Corporation | 2004/05/12 |
| Volume 3. Additional Information Report - Appendices Part 1. Submitted by Western Canadian Coal (prop) to Bob Hart (EAO) on May 12/04 | Western Canada Coal Corporation | 2004/05/12 |
| Volume 4. Additional Information Report - Appendices Part 2. Submitted by Western Canadian Coal (prop) to Bob Hart (EAO) on May 12/04. | Western Canada Coal Corporation | 2004/05/12 |
| Revised Project Description for the Wolverine Coal Project submitted to Stephen Connolly (EAO) in October 2003 | Western Canadian Coal Corp | 2003/11/06 |
| Application for the Wolverine Coal Project | David Fawcett, Western Canadian Coal Corp | 2001/12/31 |
Aboriginal Comments/Submissions |
Title | Author | Posted Date |
| Letter dated Dec 10/04 from C Willson (West Moberly First Nations) to Bob Hart (EAO) with comments on the final report for the Wolverine Coal Mine Project | Clarence Willson, West Moberly First Nations | 2004/12/21 |
| Letter dated Dec 10/04 from Lisa Taylor (Saulteau First Nations) to Bob Hart (EAO) with comments on the final recommendations report for the proposed Wolverine Coal Mine | Lisa Taylor, Saulteau First Nations | 2004/12/21 |
| Memo dated December 10/04 from Peter Homenuck (IER) to Bob Hart (EAO) with attached Final Report on the Wolverine Project | Peter Homenuck, IER Planning, Research and Management Services | 2004/12/21 |
| Memo dated Sept 21/04 from Matthew General (West Moberly and Saulteau First Nations Project Review Representative & Community Coordinator) to Bob Hart (EAO) with additional comments regarding the Wolverine Coal Project | Matthew General, Saulteau First Nation | 2004/10/04 |
| Memo dated July 21/04 from Peter Homenuck (IER) to the Wolverine Wildlife Working Group regarding First Nation issues | Peter Homenuck, IER Planning, Research and Management Services | 2004/08/24 |
| Email report dated August 2004 from Peter Homenuck (IER Planning, Research and Management Services) to Bob Hart (EAO) regarding their interim report "3rd Party Interim Report" | Peter Homenuck, IER Planning, Research and Management Services | 2004/08/10 |
| Letter dated June 11/04 from Lyle Letendre (Kelly Lake Metis Settlement Society) to Bob Hart and David Eirikson (EAO) accepting the invitation extended by Western Canadian Coal to participate in the Wolverine Coal Project - Environmental Assessment Review | Lyle Letendre, Kelly Lake Metis Settlement Society | 2004/06/14 |
| Letter dated Mar 22/04 from Chief Allan Apsassin (Saulteau First Nations) to Charles Pitcher (Western Canada Coal Corp) with regards to the consultation with the Saulteau First Nation | Chief Allan Apsassin, Saulteau First Nations | 2004/06/09 |
| Letter dated Mar 19/04 from Lyle Letendre (Kelly Lake Metis Settlement Society) to Bob Hart (EAO) regarding recent meetings and discussions | Lyle Letendre, Kelly Lake Metis Settlement Society | 2004/06/09 |
| Letter from Matthew General (Saulteau First Nations) to Norm Ringstad (EAO) with further clarification on its concerns and interests with respect to cumulative impacts/effects related to this project | Matt General, Saulteau First Nation | 2002/04/15 |
| Fax from Lana Garbitt (Saulteau First Nations) to Norm Ringstad (EAO) regarding their aboriginal rights pertaining to the Wolverine Coal Project. | Saulteau First Nation | 2002/03/13 |
EAO Generated Documents |
Title | Author | Posted Date |
| Letter dated Dec 16/04 from Bob Hart (EAO) to Councillor Clarence Willson (West Moberly First Nations) with regards to the review of the proposed Wolverine Coal Project | Bob Hart, Environmental Assessment Office | 2004/12/22 |
| Letter dated Dec 17/04 from Bob Hart (EAO) to Lisa Taylor (Saulteau First Nations) with regards to the review of the Proposed Wolverine Coal Mine Project | Bob Hart, Environmental Assessment Office | 2004/12/22 |
| Letter dated Nov 15/04 from Bob Hart (EAO) to Kathy Pomeroy (Western Canadian Coal Corporation) with regards to the formal review resuming | Bob Hart, Environmental Assessment Office | 2004/11/19 |
| Wolverine Coal Project Wildlife Working Group Action Item Update to October 10, 2004 | Bob Hart, Environmental Assessment Office | 2004/11/19 |
| Letter dated October 15/04 from Bob Hart (EAO) to Kathy Pomeroy (Proponent) regarding the temporary suspension of time limit for completion of the project review | Bob Hart, Environmental Assessment Office | 2004/10/22 |
| Wildlife Working Group: Follow-up of July 23/04 Action Items | Bob Hart, Environmental Assessment Office | 2004/09/02 |
| Wildlife Working Group: Follow-up of July 9/04 Action Items | Bob Hart, Environmental Assessment Office | 2004/09/02 |
| Wildlife Working Group Final Meeting Notes dated July 23/04 | Bob Hart, Environmental Assessment Office | 2004/08/24 |
| Project Working Group Final Meeting Minutes dated June 8/04 | Bob Hart, Environmental Assessment Office | 2004/08/23 |
| Wildlife Working Group Final Meeting Notes dated July 9/04 | Bob Hart, Environmental Assessment Office | 2004/08/23 |
| Letters dated May 31/04 from Bob Hart (EAO) to various First Nations with an invitation to participate in the review of the proposed Wolverine Coal Mine Project | Bob Hart, Environmental Assessment Office | 2004/06/10 |
| Letter dated Feb 20/04 to Hugh Taylor (West Moberly First Nation) from Bob Hart (EAO) with regards to the review of the proposed project | Bob Hart, Environmental Assessment Office | 2004/06/09 |
| Letter dated Feb 20/04 to Cliff Calliou (Kelly Lake Cree Nation) from Bob Hart (EAO) with regards to the review of the proposed project | Bob Hart, Environmental Assessment Office | 2004/06/09 |
| Letter dated Feb 20/04 to Claire Gauthier (Kelly Lake First Nation) from Bob Hart (EAO) with regards to the review of the proposed project | Bob Hart, Environmental Assessment Office | 2004/06/09 |
| Letter dated Feb 20/04 to Lyle Letendre (Kelly Lake Metis Settlement Society) from Bob Hart (EAO) with regards to the review of the proposed project | Bob Hart, Environmental Assessment Office | 2004/06/09 |
| Letter dated Feb 20/04 to Gary Gurnsey (McLeod Lake Indian Band) from Bob Hart (EAO) with regards to the review of the proposed project | Bob Hart, Environmental Assessment Office | 2004/06/09 |
| Letter dated Feb 20/04 to Chief Allan Apsassin (Saulteau First Nations) from Bob Hart (EAO) with regards to the review of the proposed project | Bob Hart, Environmental Assessment Office | 2004/06/09 |
| Letter dated May 21/04 to Charles Pitcher (Western Canadian Coal Corp) from Bob Hart (EAO) regarding the initiation of the review and public comment period for the Additional Report for the Wolverine Coal Project | Bob Hart, Environmental Assessment Office | 2004/05/28 |
| Letter dated Apr 30/04 from Joan Hesketh, DM (EAO) to Charles Pitcher (Western Canadian Coal Corp.) with regards to the Additional Information Report for Wolverine Coal Project | Deputy Minister Joan Hesketh, Environmental Assessment Office | 2004/05/20 |
| Letter dated Apr 30/04 from Bob Hart (EAO) to Charles Pitcher (Western Canadian Coal Corp) with regards to the public notification and consultation program for the Wolverine Coal Project | Bob Hart, Environmental Assessment Office | 2004/05/20 |
| Letter dated Apr 30/04 from Bob Hart (EAO) to Charles Pitcher (Western Canadian Coal Corp) with regards to the Kelly Lake communities notification and consultation program for the Wolverine Coal Project | Bob Hart, Environmental Assessment Office | 2004/05/20 |
| Letter dated Apr 30/04 from Bob Hart (EAO) to Charles Pitcher (Western Canadian Coal Corp) with regards to the First Nations notification and consultation program | Bob Hart, Environmental Assessment Office | 2004/05/20 |
| Wolverine Coal Project - Section 11 Order signed by Bob Hart on Mar 19/04 | Bob Hart, Environmental Assessment Office | 2004/03/26 |
| Wolverine Coal Project - Approved Amendments to Additional Information Requirements as identified in the Wolverine Coal Project - Project Report Specifications - March 19/04 | Bob Hart, Environmental Assessment Office | 2004/03/26 |
| Transition Order 02-18 for the Wolverine Coal Mine Project | Deputy Minister Sheila Wynn, Environmental Assessment Office | 2002/12/31 |
| Letter from Norm Ringstad (EAO) to David Fawcett (Proponent) regarding the Final Project Report Specifications | Norm Ringstad, Environmental Assessment Office | 2002/05/22 |
| Wolverine Canadian Coal Corp - Wolverine Coal Project Final Project Report Specifications May 20 2002 | Norm Ringstad, Environmental Assessment Office | 2002/05/22 |
| Letter from N Ringstad (EAO) to Dave Fawcett (Proponent) with regards to the ordering of a project report | Norm Ringstad, Environmental Assessment Office | 2002/04/15 |
| Draft Project Report Specifications for the Western Canadian Coal Corp. Wolverine Coal Project April 15, 2002 | Norm Ringstad, Environmental Assessment Office | 2002/04/15 |
| 3rd Project Committee Meeting, Final Minutes - Environmental Assessment Office, Wolverine Coal Project - March 5, 2002 Via Teleconference 9am - 11:30am. | Norm Ringstad, Environmental Assessment Office | 2002/03/18 |
| 2nd Project Committee Meeting Final Minutes - Environmental Assessment Office, Wolverine Coal Project - February 7, 2002 Via Teleconference 9:30am - 10:45pm | Garth Thoroughgood, Environmental Assessment Office | 2002/03/13 |
| Wolverine Coal Project 1st Project Committee Meeting - January 17, 2002 Room 4 Tumber Ridge Community Centre, 9am - 3:30pm - Final Meeting Minutes | Norm Ringstad, Environmental Assessment Office | 2002/02/12 |
Federal Comments/Submissions |
Title | Author | Posted Date |
| Letter from Debra Hughes (DFO) to Norm Ringstad (EAO) regarding the review of Fish and Habitat survey results in the Wolverine Project area, July 2002 report |
| 2002/12/11 |
| Fax from Debra Hughes (Fisheries & Oceans) to David Fawcett (Western Canadian Coal) regarding the March 6th, 2002 letter from David Morantz to David Fawcett. | Debra Hughes, Department of Fisheries and Oceans | 2002/03/13 |
| Letter from Debra Hughes (Habitat Biologist, Federal Govt) to Norm Ringstad (EAO) submitting DFO's comments of the Wolverine Coal Project Application Report. | Debra Hughes, Department of Fisheries and Oceans | 2002/03/01 |
| Email from Stephen Sheehan (Environment Canada) to Garth Thoroughgood (EAO) with attached documents containing Environment Canada's Review of the Wolverine Coal Project Application. | Stephen Sheehan, Environment Canada | 2002/02/18 |
Notices - News Releases |
Title | Author | Posted Date |
| Western Canadian Coal Corp. Invites the Public to an Open House June 2-3, 2004 and invites comments on the Additional Information Report | Charles Pitcher, Western Canadian Coal Corp | 2004/05/19 |
| Draft Project Report Specifications for the Wolverine Coal Project, public comment period on the draft project report specifications begins April 15, 2002 and ends on April 30, 2002 | Norm Ringstad, Environmental Assessment Office | 2002/04/15 |
| News Release from the Environmental Assessment Office regarding the public notice for invitation to comment on the application for the Wolverine Coal Project | Norm Ringstad, Environmental Assessment Office | 2002/01/02 |
Provincial Govt Comments/Submissions |
Title | Author | Posted Date |
| E-mail from Kim Belefontaine (MEM) to Bob Hart (EAO) dated Oct 7/04 indicated that ML/ARD issues are at a permitting level | Kim Bellefontaine, Ministry of Energy and Mines | 2004/12/09 |
| E-mail from Chris Carr (MEM) to Bob Hart (EAO) dated Nov 03/04 regarding the tailing dyke design | Chris Carr, Ministry of Energy & Mines | 2004/12/09 |
| E-mail from John Errington (MEM) to Bob Hart (EAO) dated July 23/04 regarding comments on the Wolverine Coal project | John Errington, Ministry of Energy and Mines | 2004/12/09 |
| E-mail from Brendan Miller (LWBC) to Bob Hart (EAO) dated Oct 25/04 regarding no outstanding issues that would effect the certificate process | Brendan G. Miller, Land and Water British Columbia Inc | 2004/12/09 |
| Memo from N.B. Carmichael (WLAP) to Bob Hart (EAO) dated Oct 28/04 regarding certificate level commitments related to water quality |
| 2004/12/09 |
| Comments dated August 16/04, with editorial changes submitted August 30/04, from John Clark (WLAP) to Bob Hart (EAO) | John Clark, Ministry of Water, Land and Air Protection | 2004/09/01 |
| Memo dated Aug 16/04 from Bruce Carmichael (MWLAP) to Bob Hart (EAO) regarding the EPD Environmental Quality Section Comments on the Information Requirements for permitting the Wolverine Mine | Bruce Carmichael, Ministry of Water, Land and Air Protection | 2004/08/19 |
| Email letter dated August 5/04 from Chris Carr (MEM) to Bob Hart (EAO) regarding their comments on the Additional Information | Chris Carr, Ministry of Energy & Mines | 2004/08/10 |
| Letter dated Aug 9/04 from Pierre Johnstone (WLAP) to Bob Hart (EAO) regarding their comments on the Additional Information. Dale Seip's Jul 26/04 email & report posted w/Wildlife Working Group Meeting Notes under EAO gen. docs on ePIC | Pierre Johnstone, Ministry of Water, Land and Air Protection | 2004/08/10 |
| Letter dated August 9/04 from Brendan Miller (LWBC) to Bob Hart (EAO) regarding their comments on the project | Brendan G. Miller, LWBC | 2004/08/10 |
| Email memo dated July 23/04 from Kim Bellefontaine (Ministry of Energy and Mines) to Bob Hart (EAO) regarding her comments on the acid rock drainage, metal leaching and water quality of the project | Kim Bellefontaine, Ministry of Energy and Mines | 2004/07/30 |
| Email dated July 23/04 from John C. Errington (Ministry of Energy and Mines) to Bob Hart (EAO) regarding his comments on reclamation | John Errington, Ministry of Energy and Mines | 2004/07/30 |
| Email dated July 23/04 from Dave Sutherland (Water, Land and Air Protection) to Bob Hart (EAO) regarding his comments on air quality | Dave Sutherland, Ministry of Water, Land and Air Protection | 2004/07/23 |
| Letter from Brian McBride (Inspector of Mines, MEM) to Dr. John Errington) submitting his comments on the Western Canadian Coal - Wolverine Coal Project Application Report. | Brian McBride, Ministry of Energy and Mines | 2002/04/05 |
| Memorandum Letter from Kim Bellefontaine (Reclamation Geologist) to Ed Beswick (Regional Manger, Prince George - Mines Branch) regarding the Preliminary Comments on ML/ARD Issues for Wolverine Coal Project - EA Application. | Kim Bellefontaine, Ministry of Energy and Mines | 2002/03/04 |
| Letter from Chris Carr (Geotechnical Engineering, MEM) to Ed Beswick (Regional Manager, MEM) submitting his comments and concerns regarding the Wolverine Coal Project Report. | Chris Carr, Ministry of Energy & Mines | 2002/03/04 |
| Letter from Bob Hart (Project Review Manager, MSRM) to Norm Ringstad (EAO) submitting his comments/information on the Wolverine Coal Project Application. | Bob Hart, Environmental Assessment Office | 2002/03/01 |
| Email from Dale Suderman (Fire Management Planner, Dawson Crk) to Garth Thoroughgood (EAO) submitting his comments and questions regarding the Wolverine Coal Project. | Dale Suderman, Ministry of Forests | 2002/02/18 |
| Email from Jim Spafford (Heritage Resource Specialist, MSRM) to Norm Ringstad (Director, EAO) submitting his comments regarding the Wolverine Coal Project Application. | Jim Spafford, Ministry of Sustainable Resource Management | 2002/01/18 |
Proponent Comments/Correspondence |
Title | Author | Posted Date |
| Final Report dated April 6/06 from Peter Homenuck (IER - Planning, Research and Management Services) entitled "Wolverine Coal Certificate and Mine Permit Amendment - Final Report" | Peter Homenuck, IER Planning, Research and Management Services | 2006/04/10 |
| Memo dated Nov 3/04 from Gord McKenna and Richard Dawson (Norwest Corporation) to Gary Gould (Western Canadian Coal) with regards to the regulatory concerns regarding Wolverine Dyke design Job # 04-2550 | Gord McKenna, Norwest Corporation | 2004/11/19 |
| Traditional Use Plant Survey received Nov 2/04 from Keystone Wildlife Research on behalf of the Proponent |
| 2004/11/19 |
| Western Canadian Coal Corporation's Wildlife Management Plan Framework received Nov /04 | Kathleen J Pomeroy, Western Canadian Coal | 2004/11/19 |
| Memo dated Nov 3/04 from Seton Stiebert (RWDI West Inc) on behalf of Proponent to Dave Sutherland (WLAP) with regards to the Wolverine Coal Dryer Furnace Bypass Operation | Seton Stiebert, RWDI West Inc | 2004/11/19 |
| Letter dated October 15/04 from Kathleen Pomeroy (proponent) to Bob Hart (EAO) regarding the remaining timelines in the review process | Kathleen J Pomeroy, Western Canadian Coal | 2004/10/22 |
| Wolverine Project Kinetic Test Update dated Sept 28/04 from Bruce Mattson (Lorax Environmental) to Bob Hart (EAO) and Kim Bellefontaine (MEM) | Bruce Mattson, Lorax Environmental | 2004/09/30 |
| Letter dated September 21/04 from Kathleen Pomeroy (Western Canadian Coal) to Bill Cooksley in response to questions posed on the Feb 25/04 open house feedback form | Kathleen J Pomeroy, Western Canadian Coal | 2004/09/29 |
| Letter dated September 21/04 from Kathleen Pomeroy (Western Canadian Coal) to Stacey Leeunesse (Tumbler Ridge) in response to questions posed on the Feb 25/04 open house feedback form | Kathleen J Pomeroy, Western Canadian Coal | 2004/09/29 |
| Letter dated September 20/04 from Kathleen Pomeroy (Western Canadian Coal) to Dale Drown (Guide Outfitters Association of BC) with regards to the Wolverine Project and Armand Didier, Guide/Outfitter | Kathleen J Pomeroy, Western Canadian Coal | 2004/09/29 |
| Letter dated September 20/04 from Kathleen Pomeroy (Western Canadian Coal) to Sue Kuethe (Koch Exploration Canada Corporation) with regards to the Wolverine Project and Koch Exploration | Kathleen J Pomeroy, Western Canadian Coal | 2004/09/29 |
| Letter dated September 21/04 from Kathleen Pomeroy (Western Canadian Coal) to Kevin Sharman (Wolverine Nordic and Mountain Society) with regards to the Wolverine Project and the Outdoors Club | Kathleen J Pomeroy, Western Canadian Coal | 2004/09/29 |
| Letter from David Fawcett (Proponent) to Mary Ann Eyben (Tumbler Ridge) acknowledging the receipt of her faxed letter dated March 13, 2002. | David Fawcett, Western Canadian Coal Corp | 2002/03/22 |
| Email from Bruce Mattson (Proponent) to Jim Stafford (Heritage Resource Specialist, MSRM) in response to his comments submitted via email on January 11, 2002. |
| 2002/02/12 |
| Email from Bruce Mattson (Proponent) to Dale Suderman (Fire Management Planner, Dawson Crk) in response to his questions and comments submitted via email on January 16, 2002. |
| 2002/02/12 |
| Email from Bruce Mattson (Lorax Environmental Services) to Mr. Saugstad (Canfor Chetwynds Office) in response to his comments submitted January 29, 2002 on the Wolverine Coal Project. |
| 2002/02/04 |
Public Comments/Submissions |
Title | Author | Posted Date |
| Letter dated August 6/04 from Susan K. Kuethe (Koch Exploration Canada Corporation) to Bob Hart (EAO) with their comments on the project | Susan K. Kuethe, Koch Exploration Canada Corporation | 2004/08/09 |
| Letter dated August 9/04 from Dale Drown (public) to Bob Hart (EAO) regarding their comments on the project | Dale Drown, Guide Outfitters Association of BC | 2004/08/09 |
| Letter received July 16/04 from Kevin Sharman (Wolverine Nordic and Mountain Society) to Bob Hart (EAO) with questions for WCC regarding the Wolverine Project | Kevin Sharman, Wolverine Nordic and Mountain Society | 2004/07/23 |
| Wolverine Coal Project June 2/04 Open House Feedback form from Jordon Pindeia (Tumbler Ridge BC) with comments | Jordan Pindeia | 2004/06/09 |
| Wolverine Coal Project June 2/04 Open House Feedback form from Fred Banham (Tumbler Ridge BC) with comments regarding the project | Fred Banham | 2004/06/09 |
| Wolverine Coal Project June 2/04 Open House Feedback form from Dawn Cooksley (Tumbler Ridge BC) with comments | Bill Cooksley | 2004/06/09 |
| Wolverine Coal Project Open House Feedback Form: Potential Issues on the Proposed Wolverine Coal Project received by Stacey Leeunesse (Tumbler Ridge BC) | Stacey Leeunesse, Northern Recreational Developments | 2004/03/12 |
| Wolverine Coal Project Open House Feedback Form: Potential Issues on the Proposed Wolverine Coal Project received by Hirko Obrandovie (Chetwynd BC) | Hirko Obradovie | 2004/03/12 |
| Wolverine Coal Project Open House Feedback Form: Potential Issues on the Proposed Wolverine Coal Project received by Bill Cooksley (Tumbler Ridge BC) | Bill Cooksley | 2004/03/12 |
| Wolverine Coal Project Open House Feedback Form: Potential Issues on the Proposed Wolverine Coal Project received by Dawn Cooksley (Tumbler Ridge BC) | Dawn Cooksley | 2004/03/12 |
| Wolverine Coal Project Open House Feedback Form: Potential Issues on the Proposed Wolverine Coal Project received by B & J Shultz (Tumbler Ridge BC) | B & J Shultz | 2004/03/12 |
| Wolverine Coal Project Open House Feedback Form: Potential Issues on the Proposed Wolverine Coal Project received by Armand Didier (Wolverine Valley Guide & Outfitters) | Armand Didier, Wolverine Valley Guide and Outfitters | 2004/03/12 |
| Letter dated Feb 29/04 from Armand Didier (Chetwynd BC) to Bob Hart (EAO) regarding the Wolverine Coal Mine | Armand Didier, Wolverine Valley Guide and Outfitters | 2004/03/02 |
| Fax from Mary Ann Eyben (Tumbler Ridge, BC) to David Pawcett (Western Canada Coal) expressing her concerns regarding the proposed location of the The Wolverine Coal Project. | Mary Ann Eyben | 2002/03/13 |
| Letter from Evan Saugstad (Divisional Forester at Canfor Chetwynd's Office) to Bruce Mattson (Proponent) submitted his concerns regarding the Wolverine Coal Project. |
| 2002/02/12 |
Amendment to Certificate Documentation |
Title | Author | Posted Date |
| Letter dated March 23/06 from Kathy Pomeroy (Western Canadian Coal Corp) to Bob Hart (EAO) regarding Wolverine Project 2.4 Mtpa Amendment - Additional Commitments | Kathleen J Pomeroy, Western Canadian Coal | 2006/04/10 |
Completed / Certified |
Notices - News Releases |
Title | Author | Posted Date |
| News Release - Coal Mine Receives Environmental Approval |
| 2005/01/18 |
EA Certificate Documentation |
Title | Author | Posted Date |
| Wolverine Coal Project - Recommendations of the Executive Director and Reasons for Recommendations | Deputy Minister Joan Hesketh, Environmental Assessment Office | 2005/01/18 |
| Wolverine Coal Project Assessment Report - December 13, 2004 | Deputy Minister Joan Hesketh, Environmental Assessment Office | 2005/01/18 |
| News Release - Coal Mine Receives Environmental Approval |
| 2005/01/18 |
| Environmental Assessment Certificate M04-01 for the Wolverine Coal Project |
| 2005/01/18 |
Amendment Certificate |
Title | Author | Posted Date |
| Amendment #2 to EA Certificate M04-01 for the Wolverine Coal Project. |
| 2007/06/08 |
| Amendment #1 to Environmental Assessment Certificate M04-01 | Bob Hart, Environmental Assessment Office | 2006/04/12 |
Amendment to Certificate Documentation |
Title | Author | Posted Date |
| Certificate Amendment Assessment Report, prepared by EAO, dated April 7, 2006 | Bob Hart, Environmental Assessment Office | 2006/04/12 |
| Advice to Executive Director, Wolverine Coal Project - Certificate Amendment | Bob Hart, Environmental Assessment Office | 2006/04/12 |
| Memo dated Mar 13/06 from Peter Homenuck (IEF)to Kathy Pomeroy (WCC) regarding the Wolverine Coal Mine Permit Application | Peter Homenuck, IER Planning, Research and Management Services | 2006/04/12 |
| Memo, with attached table, dated Mar 16/06 from Peter Homenuck (IER) to Bob Hart (EAO) regarding Wolverine Permit Application - Third Party Review | Peter Homenuck, IER Planning, Research and Management Services | 2006/04/12 |
| Summary of Comments from Independent Reviewer & Final Report dated April 6, 2006, from IER | Peter Homenuck, IER Planning, Research and Management Services | 2006/04/12 |
| Memo dated Mar 22/06 from Peter Homenuck (IER) to First Nations regarding Wolverine Permit Amendment | Peter Homenuck, IER Planning, Research and Management Services | 2006/04/12 |
| Email dated April 5/06 from Rodger Stewart (Ministry of Environment) to Bob Hart (EAO) regarding proposed changes to the draft certificate assessment report | Bob Hart, Environmental Assessment Office | 2006/04/12 |
| Minutes dated Mar 24/06 of the EAO Wolverine EA Certificate Amendment Working Group Teleconference from 10:00 a.m. to 12:15 p.m. (Pacific Time) | Bob Hart, Environmental Assessment Office | 2006/04/12 |
| First Nations and Kelly Lake Community Issues Tracking Summary dated March 17, 2006. | Kathleen J Pomeroy, Western Canadian Coal | 2006/03/24 |
| Memo dated Mar 16/06 from Peter Homenuck (IER Planning, Research and Management Services) to Bob Hart (EAO) regarding Wolverine Permit Amendment - Third Party Review | Peter Homenuck, IER Planning, Research and Management Services | 2006/03/24 |
| Meeting Summary dated June 16, 2005, regarding Wolverine Working Group Meeting #1 | Bob Hart, Environmental Assessment Office | 2006/03/24 |
| Letter dated Jan 13/06 from Kathy Pomeroy (WCC) to McLeod Lake Indian Band, Saulteau First Nation, West Moberly First Nation, Kelly Lake Cree Nation, Kelly Lake First Nation and Kelly Lake Metis Settlement Society. | Kathleen J Pomeroy, Western Canadian Coal | 2006/01/18 |
| Email dated July 28/05 from Peter Homenuck (IER Planning, Research and Management Services) to Bob Hart (EAO) regarding Third Party Review of the Wolverine Mine Permit Amendment including the Draft Table of Questions and Comments
| Peter Homenuck, IER Planning, Research and Management Services | 2005/08/02 |
| Email dated July 25/05 from Chris Carr and Kim Bellefontaine (MEM) regarding comments on the Wolverine Amendment | Chris Carr, Ministry of Energy, Mines and Petroleum Resources | 2005/07/26 |
| Letter dated June 3/05 from Bob Hart (EAO) to Kathy Pomeroy (Western Canadian Coal Corp) regarding acceptance for review of application to amend Environmental Assessment Certificate MO4-01 | Bob Hart, Environmental Assessment Office | 2005/07/06 |
| Amendment to Schedule B of Environmental Assessment Certificate for Wolverine Coal Mine Project (Commitment #95) dated June 27, 2005. |
| 2005/07/06 |
| Letter from Gary B Gould (Western Canadian Coal Corp.) to David Eirikson (EAO) with a request to amend Committment Item #95 of the Environmental Assessment Certificate | Gary B Gould, Western Canadian Coal Corp. | 2005/06/29 |
| Letter dated June 27/05 from Joan Hesketh (Associate Deputy Minister, EAO) to Gary Livingstone (Western Canadian Coal Corp) with regards to the amended Committment #95 of Schedule B of the Environmental Assessment Certificate for the Project | Joan Hesketh, Environmental Assessment Office | 2005/06/29 |
| Email dated June 20/05 from Dave Sutherland (WLAP) to Bob Hart (EAO) regarding comments on the Wolverine Certificate Amendment | Dave Sutherland, Ministry of Water, Land and Air Protection | 2005/06/22 |
| Wolverine Coal Project - Application and Appendices for Amendment to Environmental Assessment Certificate M04-01, and Mine Permit No. C-223 received June 3 2005 | Kathleen J Pomeroy, Western Canadian Coal | 2005/06/10 |
Post Certificate Documentation |
Title | Author | Posted Date |
| Letter dated Aug 21/06 from Kathy Pomeroy (WCCC) to Bob Hart (EAO) re: Pre-Production Status Update on the Wolverine Coal Mine Project. |
| 2006/08/30 |
| Email dated May 13/05 from Kathy Pomeroy (Proponent) to Bob Hart (EAO) regarding the nine Certificate Conditions | Kathleen J Pomeroy, Western Canadian Coal | 2005/05/16 |
| Email dated May 11/05 from Kathy Pomeroy (Proponent) to Bob Hart (EAO) regarding the status of the summary of Western Canadian Coal Corp.'s commitments | Kathleen J Pomeroy, Western Canadian Coal | 2005/05/12 |
|