Pre-Application |
Application Terms of Reference/Information Requirements |
Title | Author | Posted Date |
| Approved Terms of Reference dated May 23/08 for the Interior to Lower Mainland Transmission Project | Brian Murphy, Environmental Assessment Office | 2008/05/23 |
| Draft Application Terms of Reference dated June 1/07 for BC Transmission Corporation's Application for an Environmental Assessment Certificate for the Project | Melissa Holland, British Columbia Transmission Corporation | 2007/06/01 |
EAO Generated Documents |
Title | Author | Posted Date |
| Order Under Section 11 dated May 31/07 and signed by Brian Murphy, Project Assessment Director (EAO) | Brian Murphy, Environmental Assessment Office | 2007/05/31 |
| Order Under Section 10(1)(c) dated Dec. 18/06 and signed by Brian Murphy, Project Assessment Director (EAO) | Brian Murphy, Environmental Assessment Office | 2006/12/18 |
Notices - News Releases |
Title | Author | Posted Date |
| Public Invited to Comment on the Proposed Interior to Lower Mainland Transmission Project draft Terms of Reference June 11/07 to July 11/07 - Open Houses in Merritt, Kent, Coquitlam, Spuzzum and Mission | Brian Murphy, Environmental Assessment Office | 2007/06/01 |
Proponent Comments/Correspondence |
Title | Author | Posted Date |
| Public Issues Tracking Document dated Sept. 26/07 for the Interior to Lower Mainland Transmission Project Draft Terms of Reference | Sean Weston, Golder Associates Ltd. | 2007/09/27 |
| Project Description dated Mar. 13/07 for the Interior to Lower Mainland (ILM) Transmission Reinforcement Project - Nicola to Meridian Transmission Line Option | Bruce Barrett, British Columbia Transmission Corporation | 2006/12/18 |
Public Comments/Submissions |
Title | Author | Posted Date |
| Email dated July 8/07 from David Simms (Public) to EAOINFO with comments on the Draft Terms of Reference for the Project | David Simms | 2007/07/12 |
| Open House Public Comment Form from Joseph and Queenie Fasolino (Chilliwack BC) with comments on the Draft Terms of Reference for the Project | Joseph and Queenie Fasolino | 2007/07/11 |
| Email dated July 6/07 from James D. McNeil (Public) to EAOINFO with comments on the Draft Terms of Reference for the Project | James D. McNeil | 2007/07/10 |
| Email dated July 4/07 from Jan W. Jonker (Tamihi Logging Co. Ltd.) to EAOINFO with comments on the Draft Terms of Reference for the Project | Jan W. Jonker, Tamihi Logging co. Ltd. | 2007/07/05 |
| Email dated June 17/07 from Brian Kingman (Mt. Lehman BC) to EAOINFO with comments on the Draft Terms of Reference for the Project | Brian Kingman | 2007/06/18 |
| Email dated June 14/07 from John Pichugin (Teal Cedar Products Ltd.) to EAOINFO with comments on the Draft Terms of Reference for the Project | John Pichugin, Teal Cedar Products Ltd. | 2007/06/15 |
Under Review |
Application and Supporting Studies |
Title | Author | Posted Date |
| Application for an Environmental Assessment Certificate (Application) - Cover letter submitted by BC Transmission Corporation to Brian Murphy, EAO, on November 14, 2008. |
| 2008/11/14 |
| Application Table of Contents |
| 2008/11/14 |
| Application Executive Summary |
| 2008/11/14 |
| Application Acknowledgements |
| 2008/11/14 |
| Application Acronyms |
| 2008/11/14 |
| Application Glossary |
| 2008/11/14 |
| Application Table of Concordance |
| 2008/11/14 |
| Application Table of Commitments and Assurances |
| 2008/11/14 |
| Application Chapter 1 - Introduction |
| 2008/11/14 |
| Application Chapter 2- Information Distribution and Consultation |
| 2008/11/14 |
| Application Chapter 3 Review of Alternatives |
| 2008/11/14 |
| Application Chapter 4 - Project Description, Scope and Rationale |
| 2008/11/14 |
| Application Chapter 5 - Environmental Assessment Methods |
| 2008/11/14 |
| Application Chapter 6 - Environmental Effects Assessment |
| 2008/11/14 |
| Application Chapter 7 - Effects of the Environment on the Project |
| 2008/11/14 |
| Application Chapter 8 - Accidents and Malfunctions |
| 2008/11/14 |
| Application Chapter 9 - Significance of Residual Effects |
| 2008/11/14 |
| Application Chapter 10 - Cumulative Effects Assessment |
| 2008/11/14 |
| Application Chapter 11 - Environmental Management Program |
| 2008/11/14 |
| Application Chapter 12 - Environmental Monitoring and Follow-up |
| 2008/11/14 |
| Application Chapter 13 - Conclusions and Commitments |
| 2008/11/14 |
| Application Chapter 14 - List of References and Supporting Documentation |
| 2008/11/14 |
| Application Appendix A - Public Consultation & Communication Tracking Log |
| 2008/11/14 |
| Application Appendix B - First Nations Consultation Tracking Log |
| 2008/11/14 |
| Application Appendix C - Fisheries and Aquatic Habitat Assessment Technical Report |
| 2008/11/14 |
| Application Appendix D - Terrestrial Wildlife and Vegetation Assessment Technical Report |
| 2008/11/14 |
| Application Appendix E - Geotechnical and Natural Hazards Assessment Technical Report |
| 2008/11/14 |
| Application Appendix F - Surface Water Hydrology and Groundwater Assessment Technical Report |
| 2008/11/14 |
| Application Appendix G - Urban Land Use Assessment Technical Report |
| 2008/11/14 |
| Application Appendix H - Agriculture Land and Resource Use Assessment Technical Report |
| 2008/11/14 |
| Application Appendix I - Forestry Land Use Assessment Technical Report |
| 2008/11/14 |
| Application Appendix J - Land and Resource Use Assessment Technical Report |
| 2008/11/14 |
| Application Appendix K - Visual Quality Assessment Technical Report |
| 2008/11/14 |
| Application Appendix L - Contaminated Sites Assessment Technical Report |
| 2008/11/14 |
| Application Appendix M - Socio-economic Assessment Technical Report |
| 2008/11/14 |
| Application Appendix N - Air Emissions Assessment Technical Report |
| 2008/11/14 |
| Application Appendix O - Noise Assessment Technical Report |
| 2008/11/14 |
| Application Appendix P - Radio Interference Assessment Technical Report |
| 2008/11/14 |
| Application Appendix Q - Electric and Magnetic Field Baseline Survey & Modeling |
| 2008/11/14 |
| Application Appendix R - Archaeological Impact Assessment Technical Report |
| 2008/11/14 |
| Application Appendix S - Public Health Risk Assessment Technical Report |
| 2008/11/14 |
| Application Appendix T - Property Value Assessment Technical Report |
| 2008/11/14 |
| Application Appendix U - Typical Bridge and Transmission Line Watercourse Crossing Drawings |
| 2008/11/14 |
| Application Appendix V - First Nations Consultation Supporting Documentation |
| 2008/11/14 |
| Application Appendix W - Photographs of the Existing ILM Transmission System |
| 2008/11/14 |
| Application Appendix X - Typical Right-of-Way Clearing Width Diagrams |
| 2008/11/14 |
| Application Appendix Y - First Nations Interests Assessment Supporting Documentation |
| 2008/11/14 |
| Application Appendix Z - BCTC Environmental Management Documentation |
| 2008/11/14 |
| Application Appendix AA - BCTC Environmental Incident Reporting Standard |
| 2008/11/14 |
Aboriginal Comments/Submissions |
Title | Author | Posted Date |
| Brian Murphy (EAO) Response to Grand Chief Clarence Pennier (Sto:lo Tribal Council) dated 6 Mar 09 |
| 2009/03/16 |
| Tracking document comments from Muir-Grove dated 3 March 2009
|
| 2009/03/12 |
| Comments on Tracking document dated 25 Feb 09 on behalf of Matsqui First Nation |
| 2009/03/10 |
| Comments on tracking document dated 20 Feb 09 on behalf of Sto:lo Tribal Council |
| 2009/03/10 |
| Tracking document comments from Sto:lo Chiefs Council dated 26 Feb 09 |
| 2009/03/06 |
| Comments dated Feb 25/09 from Jennifer Griffith (on behalf of Matsqui First Nation) to EAO regarding the Tracking document for the ILM Project |
| 2009/02/26 |
| Comments dated Jan 26/09 from Triton consultants on behalf of the Shackan First Nation EAO regarding the ILM Project. |
| 2009/02/03 |
| Comments dated Jan 21/09 from Grand Chief Clarence Pennier (Sto:lo Tribal Council) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 21/09 from Grand Chief Clarence Pennier (Sto:lo Tribal Council) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 21/09 from Grand Chief Clarence Pennier (Sto:lo Tribal Council) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 23/09 from Chief Alice McKay (Matsqui First Nation) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 20/09 from Muir and Grove (on behalf of Hwlitsum First Nation) to EAO regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 21/09 from Chief Joe Hall (Sto:lo Nation Chief's Council) to Brian Murphy (EAO) regarding the ILM Project |
| 2009/01/26 |
EAO Generated Documents |
Title | Author | Posted Date |
| ILM Working Group Meeting Summary Dec 2, 208 |
| 2009/03/25 |
| Public & First Nations Assessment Letter - signed by Brian Murphy |
| 2008/11/07 |
| Application Acceptance Letter - signed by Brian Murphy |
| 2008/11/07 |
Federal Comments/Submissions |
Title | Author | Posted Date |
| Comments dated Feb 23/09 from Andrew Robinson (Cdn. Wildlife Service) to EAO regarding the Tracking document for the ILM Project |
| 2009/02/26 |
| Comments dated Feb 11/09 from Don Giannace (CEAA) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/02/23 |
| Comments dated Jan 23/09 from Andrew Robinson (Cdn Wildlife Service) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 23/09 from Christie MacKinlay (Health Canada) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 22/09 from Don Giannace (CEAA) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
Local Government Comments/Submissions |
Title | Author | Posted Date |
| Comments dated Feb 24/09 from Margaret Birch(City of Coquitlam) to EAO regarding the Tracking document for the ILM Project |
| 2009/02/26 |
| Comments dated Jan 23/09 from Barry Potvin (MetroVancouver Parks Dept.) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 13/09 from Margaret Birch (City of Coquitlam) to Brian Murphy (EAO) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 15/09 from Gerald H. Kingston (Fraser Valley Regional District) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/26 |
| Board Meeting Minutes and Comments dated Dec 16/08 from Gerald H. Kingston (Fraser Valley Regional District) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/21 |
| Memorandum and Comments dated Dec 8/08 from David Bennett (Fraser Valley Regional District) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/21 |
Notices - News Releases |
Title | Author | Posted Date |
| Public Comment Period and Open House Ad posted 14 November 2008. |
| 2008/11/14 |
Provincial Govt Comments/Submissions |
Title | Author | Posted Date |
| Comments dated Feb 06/09 from Mark Phillpotts(Min. of Environment) to EAO regarding the Tracking document for the ILM Project |
| 2009/02/26 |
| Comments dated Feb 24/09 from Cliff Nietvelt (Min. of Environment) to EAO regarding the Tracking document for the ILM Project |
| 2009/02/26 |
| Comments dated Feb 12/09 from Becky Brown (Min. of Agriculture & Lands) to EAO regarding the Tracking document for the ILM Project |
| 2009/02/26 |
| Comments dated Feb 20/09 from Doug Campbell (Min. of Forests and Range - Chilliwack) to EAO regarding the Tracking document for the ILM Project |
| 2009/02/26 |
| Comments dated Feb 23/09 from Sylvia Letay (MOE) to EAO regarding the Tracking document for the ILM Project |
| 2009/02/26 |
| Comments dated Jan 28/09 from Cliff Nietvelt (Min. of Environment) to EAO regarding the ILM Project |
| 2009/02/04 |
| Comments dated Jan 27/09 from Tom Blackbird(Min. of Environment) to EAO regarding the ILM Project. |
| 2009/02/03 |
| Comments dated Feb 2/09 from Sylvia Letay (Min. of Environment) to EAO regarding the ILM Project. |
| 2009/02/03 |
| Comments dated Jan 29/09 from Ian Blackburn (Min. of Environment) to EAO regarding the ILM Project |
| 2009/02/03 |
| Comments dated Jan 20/09 from Doug Campbell (Min. of Forests and Range) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 23/09 from Mark Phillpotts (MOE - Kamloops) to Brian Murphy (EAO) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 21/09 from Jeff Fournier (EPD - Lower Mainland Region) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 21/09 from Brent Moore (EPD) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 21/09 from Julie Saxton (MOE - Lower Mainland Region) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 21/09 from Ashley Smith (MOE - Lower Mainland Region) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 21/09 from Alan McCammon (MOE - EPD) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 20/09 from Martin Collins (ALC - Burnaby) to Brian Murphy (EAO) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 09/09 from Becky Brown (Ministry of Agriculture) to Brian Murphy (EAO) regarding the ILM Project |
| 2009/01/15 |
Proponent Comments/Correspondence |
Title | Author | Posted Date |
| Proponent responses to Kwantlen comments on the First Nations Tracking Table |
| 2009/04/16 |
| Response Letter from M Holland & J Ross (BCTC) to Matsqui comments dated Mar 24 2009 |
| 2009/03/31 |
| Response Letter from M Holland & J Ross (BCTC) to Hwlitsum comments dated Mar 25 2009 |
| 2009/03/31 |
| Response Letter from M Holland & J Ross (BCTC) to SNS comments dated Mar 26 2009 |
| 2009/03/31 |
| Response Letter from M Holland & J Ross (BCTC) to STC comments dated Mar 26 2009 |
| 2009/03/31 |
| Agency Issues Tracking Table Dated March 17, 2009 |
| 2009/03/25 |
| Final First Nations Consultation Report dated March 6 09. |
| 2009/03/09 |
| Interim Updated Report on FN Consultation dated Feb. 13, 2009 |
| 2009/02/20 |
| ILM Public Consultation Summary dated Feb 13, 09. |
| 2009/02/20 |
| Agency Issues Tracking Table Dated Feb 06, 2009 |
| 2009/02/16 |
| First Nations Issues Tracking Table Dated Feb 06, 2009 |
| 2009/02/16 |
| Public Issues Tracking Table Dated Feb 06, 2009 |
| 2009/02/16 |
| Letter outlining public information opportunities to date - dated Dec 5/08 |
| 2008/12/09 |
Public Comments/Submissions |
Title | Author | Posted Date |
| Comments dated Jan 23/09 from James Allard (Coquitlam) to Melissa Holland (BCTC) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 23/09 from Kurt Froehlich (Harrison Hot Springs) to EAO regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 23/09 from Casselman and Harris (Pitt Meadows) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 23/09 from Elaine Golds (BMN-Coquitlam) to EAO regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 10/09 from [Name Withheld by request] (Coquitlam) to Brian Murphy (EAO) regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 23/09 from Leo Wenk (Harrison) to EAO regarding the ILM Project. |
| 2009/01/29 |
| Comments dated Jan 19/09 from Joan Domer (Alouette Field Naturalists - Pitt Meadows) to Brian Murphy (EAO) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 16/09 from C.M. Vaishnav (Coquitlam) to Brian Murphy (EAO) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 21/09 from Duanne Vandenberg (Alouette Field Naturalists - Maple Ridge) to Brian Murphy (EAO) regarding the ILM Project |
| 2009/01/26 |
| Comments dated Jan 15/09 from Lou Cooke (Nicola Stockbreeders) to Brian Murphy (EAO) regarding the ILM Project.
|
| 2009/01/15 |
| Comments dated Dec 23/08 from Malcolm Knapp Research Forest (UBC) regarding the ILM Project. |
| 2009/01/07 |
| Comments dated Dec 2/08 from Audrey Peters regarding the ILM Project. |
| 2008/12/09 |
| Comments dated Dec 8/08 from Jeff Parrish & Cindy Bugden (Public) regarding the ILM Project. |
| 2008/12/09 |
Completed / Certified |
Notices - News Releases |
Title | Author | Posted Date |
| Information Bulletin Interior-Lower Mainland Transmission Project Approved |
| 2009/06/09 |
EA Certificate Documentation |
Title | Author | Posted Date |
| Information Bulletin Interior-Lower Mainland Transmission Project Approved |
| 2009/06/11 |
| Interior-Lower Mainland Transmission Project Recommendations of the Executive Director dated May 12, 2009 |
| 2009/06/09 |
| Interior-Lower Mainland Transmission Project Assessment Report dated May 12, 2009 |
| 2009/06/09 |
| Interior-Lower Mainland Transmission Project Environmental Assessment Certificate # E09-03 issued June 3, 2009 |
| 2009/06/09 |
|