Pre-Application |
Application Terms of Reference/Information Requirements |
Title | Author | Posted Date |
| Letter dated June 4/09 from Karen Christie (EAO) to Keith Boutcher (EPCOR) regarding amendment of the Application Terms of Reference for the proposed Quality Wind Project | Karen Christie, Environmental Assessment Office | 2009/06/04 |
| Approved Terms of Reference for the proposed Quality Wind Project dated November 2008 |
| 2008/11/21 |
| Draft Terms of Reference (dToR) for the Quality Wind Project submitted by EPCOR Power Development (Proponent) - May 2008 |
| 2008/06/25 |
EAO Generated Documents |
Title | Author | Posted Date |
| Section 13 Order issued June 4/09 by Karen Christie (EAO) amending the June 26/08 section 11 Order for the proposed Quality Wind Project | Karen Christie, Environmental Assessment Office | 2009/06/04 |
| Letter dated June 4/09 from Karen Christie (EAO) to Keith Boutcher (EPCOR) regarding amendment of the Application Terms of Reference for the proposed Quality Wind Project | Karen Christie | 2009/06/04 |
| Letter from Karen Christie (EAO) dated Nov 20/08 to Keith Boutcher (Proponent) regarding the approved Terms of Reference for the proposed Quality Wind Project | Karen Christie, Environmental Assessment Office | 2008/11/21 |
| Section 11 Order issued on June 26/08 by Karen Christie (EAO) for the proposed Quality Wind Project | Karen Christie, Environmental Assessment Office | 2008/06/27 |
| Letter dated Feb 7/08 from Derek Griffin (EAO) to Keith Boutcher (EPCOR) regarding signed section 10 Order | Derek Griffin, Environmental Assessment Office | 2008/02/08 |
Notices - News Releases |
Title | Author | Posted Date |
| Invitation to comment on the Draft Terms of Reference for the Quality Wind Project - Public comment period runs from July 2/08 to Aug 1/08 |
| 2008/06/25 |
Proponent Comments/Correspondence |
Title | Author | Posted Date |
| Letter and project description from Keith Boutcher (EPCOR) to Derek Griffin (EAO) regarding proposed Quality Wind Power Project near Tumbler Ridge | Keith Boutcher, EPCOR Power Development (BC) Limited Partnership | 2008/02/08 |
Under Review |
Application and Supporting Studies |
Title | Author | Posted Date |
| Application for an Environmental Assessment Certificate dated Jun 08/09 for the proposed Quality Wind Project |
| 2009/06/08 |
Aboriginal Comments/Submissions |
Title | Author | Posted Date |
| Kelly Lake Cree Nation Traditional Land Use Impact Report dated July 17/09 for the proposed Quality Wind Project | Gretchen Fox, Timberline Natural Resource Group | 2009/08/11 |
| Letter dated July 15/09 on the Quality Wind Project from Keith Henry on behalf of the Kelly Lake Metis Settlement Society to Tim Hicks (EAO). Historic Overview attached. | Keith Henry, KLMSS | 2009/07/20 |
| Letter dated July 17/09 on the Quality Wind Project from Linette Hodges on behalf of the Kelly Lake Cree Nation to Karen Christie (EAO) | Lynette Hodges, Kelly Lake Cree First Nation | 2009/07/20 |
EAO Generated Documents |
Title | Author | Posted Date |
| Letter dated Oct. 26/09 from Karen Christie (EAO) to Keith Boutcher (Capital Power Corporation) granting the request for a time limit suspension on the Application Review of the proposed Quality Wind Project | Karen Christie, Environmental Assessment Office | 2009/10/29 |
| Section 13 Order dated Sept. 1/09 and signed by Karen Christie amending Section 11 Order dated June 26/08 for the proposed Quality Wind Project | Karen Christie, Environmental Assessment Office | 2009/09/01 |
| Working Group Meeting Summary from meeting held in Fort St. John on June 18, 2009 regarding the Quality Wind Project | Tim Hicks, Environmental Assessment Office | 2009/08/07 |
| Letter dated June 5/09 from Karen Christie (EAO) to Keith Boutcher (EPCOR) accepting the Quality Wind Project Application for an Environmental Assessment Certificate for formal review | Karen Christie, Environmental Assessment Office | 2009/06/05 |
| Letter dated June 5/09 from Karen Christie (EAO) to Keith Boutcher (EPCOR) regarding First Nation and Public Consultation Assessment for the proposed Quality Wind Project | Karen Christie, Environmental Assessment Office | 2009/06/05 |
Federal Comments/Submissions |
Title | Author | Posted Date |
| Letter dated Oct. 21/09 from Tiffany Paul (EC-CWS) to Tim Hicks (EAO) providing review comments on the proposed Quality Wind Project Application | Tiffany Paul, Environment Canada | 2009/10/26 |
Local Government Comments/Submissions |
Title | Author | Posted Date |
| Public comments on the Quality Wind Project dated June 29/09 from Bruce Simard (Peace River Regional District) to Tim Hicks (EAO) | Bruce Simard, Peace River Regional District | 2009/07/06 |
Notices - News Releases |
Title | Author | Posted Date |
| Environmental Assessment of the proposed Quality Wind Project. Open House and Invitation to Comment June 17/09 - July 17/09. Open Houses in Tumbler Ridge June 24, Dawson Creek June 25 | Karen Christie, Environmental Assessment Office | 2009/06/08 |
Provincial Govt Comments/Submissions |
Title | Author | Posted Date |
| Email comments on the Quality Wind Project dated July 16/09 from Steve Warrington (ILMB) to Tim Hicks (EAO) | Steve Warrington, Front Counter BC | 2009/07/20 |
| Email dated July 20/09 and comments dated July 13/09 on the Quality Wind Project from Alicia Goddard (MOE) to Tim Hicks (EAO) | Alicia Goddard, MOE ES Division | 2009/07/20 |
Proponent Comments/Correspondence |
Title | Author | Posted Date |
| Letter dated Oct. 23/09 from Keith Boutcher (Capital Power Corporation) to Karen Christie (EAO) requesting a time limit suspension on the Application Review of the proposed Quality Wind Project | Keith Boutcher, CP Renewable Energy (BC) Limited Partnership | 2009/10/29 |
| Quality Wind Project Public Consultation Report dated Aug. 10/09 | Jay Shukin, EPCOR | 2009/10/20 |
| Public Comments Tracking Table dated Aug. 10/09 for the proposed Quality Wind Project | Ashleigh Ballevona, Hemmera Envirochem Inc. | 2009/08/12 |
| Letter received Jul 30/09 from Keith Boutcher (Capital Power Corporation) to Karen Christie (EAO) regarding the transition from EPCOR Utilities Inc. to Capital Power Corporation | Keith Boutcher, CP Renewable Energy (BC) Limited Partnership | 2009/08/07 |
Public Comments/Submissions |
Title | Author | Posted Date |
| Public comments on the Quality Wind Project dated July 16/09 from Terry Wardrop (Quad Riders ATV Association of BC) to Karen Christie (EAO) |
| 2009/07/20 |
| Public comments on the Quality Wind Project dated July 3/09 from Neil Findlay (Kamloops BC) to Karen Christie (EAO) |
| 2009/07/08 |
| Public comments on the Quality Wind Project dated June 24/09 from Rae Moore (Tumbler Ridge BC) to Karen Christie (EAO) |
| 2009/07/02 |
| Public comments on the Quality Wind Project dated June 24/09 from Ray Goldade (Tumbler Ridge BC) to Karen Christie (EAO) |
| 2009/07/02 |
| Public comments on the Quality Wind Project dated June 24/09 from Ellis E. Howard (Tumbler Ridge BC) to Karen Christie (EAO) |
| 2009/07/02 |
| Public comments on the Quality Wind Project dated June 25/09 from Roy Mumby (Dawson Creek BC) to Karen Christie (EAO) |
| 2009/07/02 |
Concurrent Permitting |
Title | Author | Posted Date |
| Letter dated Mar 13/09 from Karen Christie (EAO) to Fred Shafai (EPCOR) acknowledging receipt of Application for Concurrent Review of Crown Land Tenure for the Quality Wind Project and acceptance of Application | Karen Christie, Environmental Assessment Office | 2009/06/11 |
| Letter dated Feb 19/09 from Fred Shafai (EPCOR) to Robin Junger (EAO) regarding Application for Concurrent Review of Crown Land Tenure for the Quality Wind Project | Fred Shafai, EPCOR | 2009/06/10 |
|