Kamloops Groundwater Project

Type:Typical EA Process (Active and Complete)Status:Completed / Certified
Category:Water ManagementPre-application

Start Date:

2000/11/10
 

Document Index

Under Review

Application and Supporting Studies

Title

Author

Posted Date

Kamloops Groundwater Application for a Project Approval CertificateBruce Bosdet, Golder Associates Ltd2000/11/14

EAO Generated Documents

Title

Author

Posted Date

Kamloops Groundwater Project - Order Under Section 11 dated Feb 27/04 signed by Anne CurrieAnne Currie, Environmental Assessment Office2004/03/05
Letter dated Mar 3/03 from Sheila Wynn (Deputy Minister, EAO) to Stephen Connolly (EAO) regarding Delegation of AuthorityDeputy Minister Sheila Wynn, Environmental Assessment Office2003/09/24
Transition Order 02-10 Kamloops Groundwater Project Deputy Minister Sheila Wynn, Environmental Assessment Office2002/12/31
Letter from Garry Alexander (EAO) to Maurice Gravelle (City of Kamloops) regarding the Extension of Time Order for the City of Kamloops Groundwater Well ProjectGarry Alexander, Environmental Assessment Office2002/10/07
Extension of Time Order signed by Honourable Stan Hagen on October 2 2002  2002/10/07
Letter from Sheila Wynn (DM EAO) to Hounourable Stan Hagen seeking the approval and signature of the Extension of the Time Order on the Kamloops Groundwater ProjectDeputy Minister Sheila Wynn, Environmental Assessment Office2002/10/07
Memo from Sheila Wynn (DM, EAO) to Garry Alexander (EAO) delegating the powers and duties assigned to the Executive Director under section 9(5) and rescinding the powers and duties that were previously delegated to Marcia Farquhar (EAO).Deputy Minister Sheila Wynn, Environmental Assessment Office2002/07/19
Extension of time order dated July 4, 2002.Marcia Farquhar, Environmental Assessment Office2002/07/10
Extension of Time Order (December 6, 2001) to allow the City to install a test collector well at McArthur Island and conduct a pumping test to confirm the aquifer characteristics and water quality.Honourable Stan Hagen, Sustainable Resource Management2001/12/12
Kamloops Groundwater Project Final Meeting Minutes (Teleconference, January 11, 2001at 1:30PM to 2:30PM)Marcia Farquhar, Environmental Assessment Office2001/02/13
Letter from M. Farquhar (EAO) to D. and L. Rice, S. Durant, C. Town, B. Scott, J. Baglee, and R. Madsen (all Kamloops) regarding ETO.Marcia Farquhar, Environmental Assessment Office2001/01/31
Kamloops Groundwater Final Meeting Minutes (By Videoconference at 3rd Floor - 940 Blanshard Street, Victoria BC and Room 1A/1B - 523 Columbia Street, Kamloops BC, November 29, 2000 at 1:00pm to 3:35pm)Marcia Farquhar, Environmental Assessment Office2001/01/23
Extension of Time Order (January 17, 2001) to allow the City to install a test collector well at McArthur Island and conduct a pumping test to confirm the aquifer characteristics and water quality.Ian Waddell, Ministry of Environment, Lands and Parks2001/01/22
Letter from M Farquhar (EAO) to Proponent with regards to the opportunity to respond on public/agency comments on the applicationMarcia Farquhar, Environmental Assessment Office2000/12/22
Letter from M Farquhar (EAO) to Proponent regarding opportunity to respond to public comments on the projectMarcia Farquhar, Environmental Assessment Office2000/12/13
Letter from M Farquhar (EAO) to Proponent regarding the assessment of the Public/First Nations consultation program for the Kamloops Groundwater ProjectMarcia Farquhar, Environmental Assessment Office2000/12/04
Letter from M Farquhar (EAO) to Chief M Jules (Kamloops Indian Band) with regards to Kamloops Groundwater Project and an invitation to sit on the project committeeMarcia Farquhar, Environmental Assessment Office2000/11/20
Letter from M Farquhar (EAO) to M Gravelle, City of Kamloops (Proponent) regarding acceptance of Application for a Project Approval Certificate for the Kamloops Groundwater ProjectMarcia Farquhar, Environmental Assessment Office2000/11/14
Open letter on the proposed Kamloops Groundwater Project Review inviting public comment on the application by December 18, 2000Marcia Farquhar, Environmental Assessment Office2000/11/14

Notices - News Releases

Title

Author

Posted Date

EAO Registry Notice - Extension of Review Time Ordered (December 6, 2001)Marcia Farquhar, Environmental Assessment Office2001/12/12
EAO Registry Notice - Extension of Review Time Ordered (January 17, 2001)Marcia Farquhar, Environmental Assessment Office2001/01/23
Environmental Assessment Notice - Public Comment Invited on an Application for Kamloops Groundwater ProjectMarcia Farquhar, Environmental Assessment Office2000/11/14

Provincial Govt Comments/Submissions

Title

Author

Posted Date

Email dated Oct 1/03 from Bob Grace (WLAP) to Stephen Connolly (EAO) with regards to his review of Chapter 1 - Water Quality of Golder's Final Report  2003/10/07
Email dated Sept 29/03 from Des Anderson (WLAP) to Stephen Connolly (EAO) with regards to reviewing the report by IWS and Golder AssociatesDes Anderson, Ministry of Water, Land and Air Protection2003/09/30
Email from P Bailey (MAA) to K Hardie (EAO) stating the consultant, on behalf of the proponent have covered all aspects of concern that might possibly be addressed at this stage of the projectPeter Bailey, Ministry of Community, Aboriginal and Womens Services2000/12/22
Email from D Hutchcroft (SBTC) to M Farquhar (EAO) with comments on the Kamloops Groundwater Project ApplicationDave Hutchcroft, Ministry of Sustainable Resource Management2000/12/22
Letter from V Carmichael (MELP) to M Farquhar (EAO) with comments on the Kamloops Groundwater Project ApplicationVicki Carmichael, Environmental Assessment Office2000/12/21

Proponent Comments/Correspondence

Title

Author

Posted Date

Letter dated Sept 17/03 from Golder Associates to S Connolly (EAO) submitting additional information regarding the testing of City of Kamloops' Test Collector  2003/09/24
Letter from Bruce Bosdet (proponent) to Marcia Farquhar (EAO) requesting a further timeline extension.Bruce Bosdet, Golder Associates Ltd2002/06/27
Fax from Bruce Bosdet (proponent) to Marcia Farquhar (EAO) requesting a timeline extension to June 30, 2002 for the Kamloops Groundwater Project.Bruce Bosdet, Golder Associates Ltd2001/11/29
Letter from Golder Associates (on behalf of proponent) to M. Farquhar (EAO) re. Commitments regarding pumping test schedule review and Slough Crossing Schedule Groundwater Collector Well.Bruce Bosdet, Golder Associates Ltd2001/01/18
Letter from Golder Associates (on behalf of Proponent) to M Farquhar (EAO) with a request for a timeline extensionBruce Bosdet, Golder Associates Ltd2000/12/22
Letter from Golder Associates (on behalf of Proponent) to M Farquhar (EAO) with regards to the committment to monitor and mitigate drawdown effects on riparian vegetation groundwater collector wellBruce Bosdet, Golder Associates Ltd2000/12/18
Archaeological Impact Assessment Proposed Water Collector Well and Associated Developments Report from Golder Associates Ltd (on behalf of Proponent) to M Farquhar (EAO)Bruce Bosdet, Golder Associates Ltd2000/12/18
Response letters from Proponent to public comments and letter to M Farquhar (EAO) with regards to the commitment to conduct archaeological monitoring during trenching on North side of slough groundwater collector wellBruce Bosdet, Golder Associates Ltd2000/01/03

Public Comments/Submissions

Title

Author

Posted Date

Letter from R Madsen (Thompson Institute of Environmental Studies) to EAO with concerns regarding the Kamloops Groundwater Project  2000/12/22
Letter from B Scott (Thompson Watershed Coalition) to M Farquhar (EAO) with comments regarding the proposed projectBronwen Scott, Thompson Watershed Coalition2000/12/18
Email from L Rice (Kamloops, BC) to M Farquhar (EAO) in favour of the proposed groundwater well and commentsDesmond and Louise Rice2000/12/18
Letter from J Baglee (Kamloops, BC) to M Farquhar (EAO) with regards to the proposed projectJennifer Baglee2000/12/14
Email from D Rice (Kamloops, BC) to M Farquhar (EAO) with support of the proposed projectDesmond and Louise Rice2000/12/09
Letter from S Durant (Kamlooops, BC) to M Farquhar (EAO) with comments regarding the proposed project  2000/11/30
Email from C Town (Kamloops, BC) to M Farquhar (EAO) with support for the Kamloops Groundwater ProjectChris Town2000/11/24

Completed / Certified

Notices - News Releases

Title

Author

Posted Date

Information Bulletin - Certificate Assures Safe Water Alternative for Kamloops  2004/04/14

EA Certificate Documentation

Title

Author

Posted Date

Environmental Assessment Certificate W04-02 for the Kamloops Groundwater Project  2004/04/14
Kamloops Groundwater Project Assessment ReportAnne Currie, Environmental Assessment Office2004/04/14
Kamloops Goundwater Project - Recommendations of the Executive Director and Reasons for RecommendationsDeputy Minister Joan Hesketh, Environmental Assessment Office2004/04/14
Information Bulletin - Certificate Assures Safe Water Alternative for Kamloops  2004/04/14
Last Updated: 2009-11-20
Copyright.Disclaimer.Privacy.Accessibility.