Port Alberni Generation Project

Type:Withdrawn from EA ProcessStatus:Withdrawn
Category:EnergyPre-application

Start Date:

2001/06/08

Under Review EAO Generated Documents



Folder

Date Posted

Letter from Jan Hagen (EAO) to Lachlan Russel (project manager, PAGP partnership) regarding acceptance of the Application.Unknown
Letter from Jan Hagen (EAO) to project reviewers (see distribution list) regarding the project review with attached Guidelines for Submission of Agency Review Comments.Unknown
Letter from Jan Hagen (EAO) to Project Committee (see distribution list) regarding the project review under the EAA and identification of permit information reviews with attachments.Unknown
Email from Jan Hagen (EAO) to EAO PAGP Active Committee members formally advising them that the Project Committee has been formed.Unknown
Letter from Jan Hagen (EAO) to Lachlan Russel (project manager) regarding acknowledgement of receipt of an Application for the Port Alberni Generation Project fro screening.Unknown
Email from Jan Hagen (EAO) to the project committee and proponent regarding the screening of the application and providing comments on the application with attachments.Unknown
Memo from Jan Hagen (EAO) to Denis White (CEO, Port Alberni Port Authority) regarding participating on the Project Committee.Unknown
Letter from Jan Hagen (EAO) to Lachlan Russel (Proponent) requesting additional information.Unknown
Letter from Jan Hagen (EAO) to Lachlan Russel (Proponent) regarding assessment of Public/First Nations consultation program.Unknown
Letter from Jan Hagen (EAO) to Lachlan Russel (Proponent) regarding some clarification requested by the Project Committee.Unknown
Email from Jan Hagen (EAO) to Bernadette Wyton (Citizens Stewardship Coalition) from regarding Jan's acknowledgement of the receipt of her letter of July 26, 2001.Unknown
Letter from Jan Hagen (EAO) to Lachlan Russel (Project Manager, PAGP) regarding the project committee meeting in Port Alberni on July 26, 2001.Unknown
Email from Jan Hagen (EAO) to Jim McManus (ACRD) regarding previous requested documents provided under another review process.Unknown
Port Alberni Generation Project Partnership - Port Alberni Generation Project Review. First Project Meeting - Echo Field House, Port Alberni, BC (And by confernce call) - July 10 2001 - 9am to 5pmUnknown
Email from Jan Hagen (EAO) to Jim McManus (ACRD) regarding a expedient follow up on an action from the July 26 PC meeting.Unknown
Email from Jan Hagen (EAO) to Lachlan Russel (Proponent) regarding the signed letters by BCH and PCI.Unknown
Email from Jan Hagen (EAO) to Jim McManus (Proponent) regarding the chambers blank survey form.Unknown
Emails from Jan Hagen (EAO) to Lachlan Russel (BC Hydro) regarding PPI agreement in principal to let BC Hydro/Calpine use their sewage lagoon.Unknown
Email from Jan Hagen (EAO) to Bernadette Wyton (PACSC, Alberni Valley Chamber of Commerce) regarding the public tour of the Island Cogeneration Project.Unknown
Letter from Jan Hagen (EAO) to Jim McManus (Director of Planning, Alberni-Clayoquot Regional) regrding Mr. McManus' request for the public hearing documentation from the City of Port Alberni.Unknown
Email from Jan Hagen (EAO) to EAO PAGP active committee members and EAO PAGP advisors regarding the acknowledgement of 33 signed form letters in support of the project from the Port Alberni Chamber of Commerce.Unknown
Email from Jan Hagen (EAO) to Lachlan Russell (Proponent) regarding GHG from twinning of Centra pipeline for the PAGP.Unknown
Fax from Jim McManus (ACRD) to Jan Hagen (EAO) forwarding copies of correspondence between Lachlan Russel and Pacifica Lagoon.Unknown
Email from Jan Hagen (EAO) to PAGP Advisors and Active members acknowledging receipt of 28 more approval forms from the Alberni Valley Chamber of Commerce.Unknown
Email from Jan Hagen (EAO) to Lachlan Russel (Project Manager, BC Hydro) & Steve McNaughton (Ministry of Sustainable Resource Management) regarding the reciept of a fax letter from Judith Sayers (Hupacasath First Nation) about the impacts of air emissionsUnknown
Email from Cheryl Kitching (PAGP) to Jan Hagen (EAO) with attached Letter regarding supplementary information on Calpuff plots.Unknown
Email from Cheryl Kitching (PAGP) to Jan Hagen (EAO) regarding Supplementary information to Inversions.Unknown
Email with attached letter from Cheryl Kitching (PAGP) to Jan Hagen (EAO) in rsponse to August 10, 2001 letter from Chief Judith Sayers.Unknown
Port Alberni Generation Project Final Meeting Minutes (The Coast Hospitality Inn, 3835 Redford St, Port Alberni BC, July 26, 2001 - 9:30 to 4:30).Unknown
Email from Jan Hagen (EAO) to Arthur Caldicott (Port Alberni) in response to his previous email submitted on the project.Unknown
Note from Jan Hagen (EAO) to record to file a record of individuals phoning EAO declaring a position for or against the project.Unknown
Email from Jan Hagen (EAO) to Arthur Caldicott (Cobble Hill) in response to his comments regarding a Stage 3 for the project.Unknown
Email from Jan Hagen (EAO) to Bernadette Wyton (Port Alberni Citizens Stewardship Coalition) acknowledging receipt of her letter and package on August 27, 2001.Unknown
Email from Tony Pearse (Consultant) to Jan Hagen (EAO) with attached documents on behalf of the Hupacasath First Nations.Unknown
Email from Steve McNaughton (Ministry of Sustainable Resource Management) to Jan Hagen (EAO) regarding a follow-up from Setember 17, 2001 meeting.Unknown
Email from Jan Hagen (EAO) to PAGP Active Committee members and Advisors regarding PAGP - Omnibus.Unknown
Email (with attachment) from Karie Hardie (EAO) to Jeanette Barker (Port Alberni) regarding Dr. Rockwell's letter.Unknown
Email from Jan Hagen (EAO) to PAGP committee members and advisors regarding public support.Unknown
Letter from Sheila Wynn (Deputy Minister, EAO) to Lachlan Russel (Proponent) regarding the Review of Application for Approval of Port Alberni Generation project under the Environmental Assessment Act. Order requiring a Project Report.Unknown
Letter from Jan Hagen (EAO) to Sheila Wynn (Deputy Minister, EAO) regarding Review of the Port Alberni Generation project under the Environmental Assessemnt Act. Project Committee Recommendations.Unknown
Draft Project Report Specifications, prepared by the PAGP Project Committee.Unknown
Memorandum from Jan Hagen (EAO) to Sheila Wynn (Deputy Minister, EAO) regarding the review of the PAGP Draft Project Report Specifications with enclosed Draft Specs & Summary of PC recommendations.Unknown
Port Alberni Generation Project. Review of Application for a project Approval Certificate. Development of Stage 2 Draft Project Report Specifications. Summary of Project Committee Recommendations.Unknown
Letter from Sheila Wynn (Deputy Minister, EAO) to Lachlan Russel (Proponent) regarding Draft Project Report Specificaitons for the PAGP with enclosed Draft Specifications.Unknown
Letter from Jan Hagen (EAO) to Lachlan Russel (Proponent) regarding assessment of Public/First Nations consultation Program for the proposed PAGP.Unknown
Letter from Sheila Wynn (Deputy Minister, EAO) to Lachlan Russel (Proponent) regarding a change in the public comment start and end dates.Unknown
Letter from Jan Hagen (EAO) to Lachlan Russel (BC Hydro) in response to BC Hydro's November 27, 2001.Unknown
Final Meeting minutes for the Third Project Committee meeting held on August 15 20012002/01/29
Final Meeting minutes for the fourth project committee meeting held on September 17 2001 in Nanaimo2002/01/29
Final Meeting minutes for the fifth project committee meeting held on October 4th 2001 in Port Alberni2002/01/29
Final Meeting minutes for the sixth project committee meeting held on October 10 2001 in Victoria2002/01/29
Final Meeting minutes for the seventh project committee meeting held on October 18th 2001 in Nanaimo2002/01/29
Final Meeting minutes for the eighth project committee meeting held on October 30th 2001 in Nanaimo2002/01/29
Final Meeting minutes for the ninth project committee meeting held on November 7th 2001 in Victoria2002/01/29
Last Updated: 2009-11-21
Copyright.Disclaimer.Privacy.Accessibility.