Folder | Date Posted |
| Time Limit Extension Order-Jumbo Glacier Resort Project | 2004/09/15 |
| Report - Review of RK Heli-Ski-Comments Received on Sierra Systems Report - Prepared by Sierra Systems Group August 20, 2004 | 2004/08/25 |
| Report - Review of Iris Environmental Systems Independent Feasibility Study for the Jumbo Glacier Resort Project - Prepared by SE Group June 2004 | 2004/08/04 |
| Report - Jumbo Valley Assessment - Prepared by Sierra Systems Group July 28, 2004 | 2004/08/04 |
| Feasibility Working Group Minutes for June 4/04 | 2004/07/28 |
| Jumbo Glacier Resort Project Meeting Minutes for the May 19/04 Governance Working Group Meeting | 2004/07/28 |
| Letter dated June 28/04 from Martyn Glassman (EAO) to Oberto Oberti (Proponent) acknowledging receipt of their Project Report Supplement (Birds) for the project | 2004/06/29 |
| Jumbo Glacier Resort Project Meeting Minutes for the May 18/04 Technical Advisory Committee Meeting #3 | 2004/06/11 |
| Open House Summary Report dated April 2004 | 2004/05/05 |
| Jumbo Glacier Resort Project Meeting Minutes for the Apr 1/04 Technical Advisory Committee Meeting #2 | 2004/05/05 |
| Jumbo Glacier Resort Project Meeting Minutes for the Feb 24/04 Technical Advisory Committee Meeting | 2004/03/08 |
| Jumbo Glacier Resort Project - Project Details | 2004/03/08 |
| Assessment of the adequacy of the Proponent's Public Consultation Program, issued by Martyn Glassman (EAO) on Jan 28, 2004. | 2004/01/29 |
| Time Limit Extension Order issued Jan 27, 2004 by Joan Hesketh (DM) for the Jumbo Glacier Resort Project. | 2004/01/28 |
| Cover letter dated Jan 27, 2004 from Joan Hesketh (DM) to Oberto Oberti (Proponent) regarding a Time Limit Extension Order for the Jumbo Glacier Resort Project. | 2004/01/28 |
| Letter dated Jan 27, 2003 from Martyn Glassman (EAO) to Oberto Oberti (Proponent) accepting the Project Report dated Dec 31, 2003. | 2004/01/28 |
| Section 11 Procedural Order for the EA Review of the Jumbo Glacier Resort Project issued by Martyn Glassman (EAO) on Jan 27, 2004 . | 2004/01/28 |
| Letter dated Dec 31, 2003 from Martyn Glassman (EAO) to Oberto Oberti (Proponent) acknowledging receipt of the Jumbo Glacier Resort Project Report on Dec 30, 2003. | 2003/12/31 |
| EAO NOTE: All NEW project information posted since the EA Act (2003) was proclaimed on 30-Dec-2002 appears ABOVE this separator. | 2003/12/30 |
| Meeting Minutes for the Oct 28/03 Provincial Review Agencies Update Session | 2003/11/20 |
| Transition Order 02-09 Jumbo Glacier Alpine Resort Project. | 2003/10/06 |
| Letter from Raymond Crook (EAO) to Roger Madson (Heli-Ski Panorama Inc.) with attached Jumbo Glacier Alpine Resort Project Review Update document in response to his inquiry about the status of the project. | 2001/10/15 |
| Response letter from Sheila Wynn (EAO) to Rowena Eloise (West Kooteny Coalition for Jumbo Wild) regarding letter of December 5, 2000 (included) and EA Process. | 2001/01/31 |
| Jumbo revised meeting minutes (teleconference November 17, 2000) | 2001/01/18 |
| Response letter from S Wynn (DM EAO) to J Pinsonneault (Windermere, BC) with regards to the Jumbo Glacier alpine resort project | 2000/12/04 |
| Letter from R Crook (EAO) to I Cobb (The Valley Echo) with clarification of the environmental assessment review process | 2000/09/11 |
| Email from Alan Calder to Ray Crook. RE: grizzly report by Matt Austin. | 2000/08/24 |
| Implications Assessment of the Proposed Jumbo Glacier Alpine Resort for R.K. Heli-Ski Panorama Inc.'s Operations. Prepared by Brent Harley and Associates Inc. November 1999. | 2000/07/05 |
| Letter from S Wynn (DM EAO) to C McIIwane with comments on the project | 2000/06/13 |
| Letter from S Wynn (Deputy Minister EAO) to E Mallam with comments on the Jumbo Glacier Alpine Resort | 2000/05/23 |
| Letter from S Wynn (DM EAO) to the Funnells responding to their opposition to the Jumbo Glacier Alpine Resort | 2000/05/04 |
| Letter from R Crook (EAO) to Project Committee regarding the distribution of the AXYS Grizzly Bear DNA Study | 1999/12/10 |
| Jumbo Glacier Alpine Resort Project Review - Public Advisory Committee (PAC) Terms of Reference - First Draft. | 1999/11/19 |
| Response letter on behalf of Glen Clark, Premier fr. Sheila Wynn DM of EAO to Dan Hicks of Prince George, BC with regards to the Jumbo Glacier Project | 1999/05/25 |
| Letter fr. R. Crook of EAO to prop with regards to the proposed Jumbo Glacier Alpine Resort Project-Independent RK Heli-Ski Study | 1999/05/03 |
| Letter fr. Ray Crook of EAO to Roger Madson of RK Heli-Ski Panorama Inc RE: Proposed Jumbo Glacier Alpine Resort Project-Independent RK Heli-Ski Study | 1999/05/03 |
| Letter fr. S. Wynn, DM of EAO to S. Sutmoller with regards to the Jumbo Glacier Alpine Resort. | 1999/04/29 |
| Response letter fr. S. Wynn to L. Funnell on behalf of Glen Clark, Premier regarding Jumbo Glacier Alpine Resort. | 1999/03/09 |
| Response letter fr. S. Wynn DM of EAO to D. Gordon regarding the proposed Jumbo Glacier Alpine Resort. | 1999/02/23 |
| Response letter fr. S. Wynn, DM of EAO to B. Cullen with regards to the Jumbo Glacier Alpine Resort. | 1999/02/23 |
| Response letter fr. S. Wynn, MD of EAO to A. Kraayvanger regarding the proposed Jumbo Glacier Alpine Resort. | 1999/02/22 |
| Memo fr. R Crook (EAO) to Project Committee Members re: Distribution of Matt Lowe's critique of Final Project Report Specifications | 1999/01/26 |
| Letter fr. S Wynn, DM of EAO to L Sheps regarding comments being forwarded to R Crook of EAO. | 1999/01/04 |
| Email fr. R Crook of EAO to PC with regards to brief update on status of project review. | 1998/12/29 |
| Response letter fr. S Wynn, DM of EAO to M Kraayvanger with regards to Jumbo Glacier Alpine Resort. | 1998/12/17 |
| Response letter fr. S. Wynn, DM of EAO to D. Eller with regards to comments being forwarded to Ray Crook of EAO. | 1998/12/08 |
| Response letter fr. S. Wynn to.G.Browne on behalf of Glen Clark, Premier with regards to the proposed Jumbo Glacier Alpine Resort | 1998/12/04 |
| Response letter fr. S. Wynn, DM of EAO to. J. Moore on behalf of Glen Clark, Premier with regards to the proposed Jumbo Glacier Alpine Resort. | 1998/12/04 |
| Response letter fr. S Wynn, DM of EAO to J Moore with regards to Jumbo Glacier Alpine Resort Project | 1998/11/26 |
| Response letter fr. R Crook of EAO to J Tsai advising of Timeline Extension. | 1998/11/19 |
| Response letter fr. S Wynn (DM EAO) to G Maryniak with regards to Jumbo project | 1998/11/06 |
| Response letter fr. S. Wynn (Deputy Minister EAO) to Public Re: concerns to specific points raised on the Jumbo Project | 1998/10/19 |
| Letter fr. R Crook (EAO) to P Wenger (Nelson Pennywise) re: Environmental Assessment of Jumbo Glacier Project | 1998/10/09 |
| Response letter fr. S Wynn DM of EAO to H Dahle with regards to Jumbo Glacier Alpine Resort | 1998/10/05 |
| Memo fr. Ray Crook of EAO to PC members Re: revised minutes of May 1,1998 PC Meeting | 1998/09/30 |
| Response letter fr. Sheila Wynn DM of EAO to Michael Risden with regards to the Jumbo Glacier Alpine Resort | 1998/09/30 |
| Response letter fr. S. Wynn (EAO) to G. Patterson with regards to the Jumbo Glacier Alpine Resort | 1998/09/23 |
| Letter fr. R. Crook (EAO) to Mayor G. Deck (Radium Hot Springs) re: Role of Land Use Plan in Decision Making, Jumbo Glacier | 1998/09/15 |
| Letter fr. R Crook (EAO) to G. Bednard (Forest Land Commission) RE: Finalized Project Report Specifications for Jumbo. | 1998/09/04 |
| Letter fr. R. Crook (EAO) to B Salter (BC Hydro) RE: Finalized Project Report Specifications | 1998/09/04 |
| Response letter fr. S. Wynn (DM EAO) to CLK Mellwane with regards to Jumbo Glacier Alpine Resort | 1998/09/04 |
| Revised Minutes from Jumbo Glacier Project Committee meeting Feb.27/97 in Cranbrook, BC | 1998/08/10 |
| letter from Sheila Wynn DM, EAO to Kathleen Sparks of Kaslo BC regarding Jumbo Glacier. Attch. letter from Kathleen Sparks to Glen Clark re: Jumbo | 1998/07/30 |
| Letter fr. Sheila Wynn, DM of EAO to Diane Colins & family in response to letter with comments on the Jumbo project. | 1998/07/24 |
| Letter fr. S. Wynn, DM of EAO to R. Wege explaining EAO's involvement & procedures in the Project. Encl: Letter fr. R. Wege to Glen Clark, Premier | 1998/07/17 |
| Letter fr. D. Williamson (Environmental Consulting) to O. Oberti (Proponent) on Snow making procedures and related experience in snowmaking | 1998/07/17 |
| Letter fr. S. Wynn, DM of EAO to H. Hutter in regards to the explanation of the Jumbo project of why the project is being assessed | 1998/07/06 |
| Response letter to P Dobruski (Public) fr. S. Wynn (Deputy Min. EAO) in regards to assessing concerns over Grizzly bears and the Jumbo resort. | 1998/07/06 |
| Response letter fr. Raymond Crook of EAO to Roger Madson of R K Heli-Ski with the status of the Jumbo review | 1998/06/17 |
| Environmental Assessment of Jumbo Glacier Alpine Resort Project-Finalised Project Report Specifications from Ray Crook to Public Advisory Committee) | 1998/06/12 |
| Extension of Time Order #2 for the Jumbo Glacier Project sighed by Cathy McGregor of (MELP) on June 5/98 | 1998/06/12 |
| subject: Jumbo Glacier resort project - finalized specifications Email from Raymond Crook of EAO sent to members of the Project Committee and Other Review Agencies noting that copies of the project report specifications are finalized and enroute next week | 1998/05/25 |
| Clarification of common questions regarding the Jumbo Glacier Resort Project dated May 20, 1998 | 1998/05/20 |
| Letter from DM Sheila Wynn of EAO sent to Graham Sparrow of Calgary AB Letter written in response to a letter of opposition written to Premier Glen Clark of BC on Feburary 18, 1998. | 1998/04/29 |
| re: Jumbo Glacier Alpine Resort Project MEMO from Raymond Crook of EAO sent to Pia Archibald of MELP forwarding information submitted by the proponent. | 1998/04/29 |
| Letter from Raymond Crook of EAO sent to Oberto Oberti of Pheidias Project Management Corporation (Proponent) with revised minutes of the meetings between review ministries. | 1998/04/27 |
| Email from Raymond Crook of EAO sent to the Project Committee Members and Other Review Agencies noting that EAO is mailing a copy of the revised draft project report specifications and noting the meeting on May 1, 1998 in Cranbrook. | 1998/04/22 |
| MEMO from Raymond Crook of EAO sent to the Jumbo Glacier Project Committee Members and Other Review Agencies (distribution list attached) noting the next meeting of the project committee. | 1998/04/21 |
| Letter from Ray Crook of EAO to Oberto Oberti of Pheidias Project Management Corporation (Proponent) noting that previous correspondence regarding the provincial system for producing maps has been forwarded to Pia Archibald of MELP. | 1998/04/21 |
| Letter from DM Sheila Wynn of EAO to Duanne Vandenberg of Maple Ridge BC Letter responds to a letter sent to the Premier (Glen Clark) of BC opposing the Jumbo Glacier Alpine Resort project. | 1998/04/15 |
| Letter from Raymond Crook of EAO sent to Oberto Oberti (proponent) confirming meeting set for March 11, 1998 in Victoria. | 1998/03/13 |
| Letter from Raymond Crook of EAO sent to Project Committee members by FAX (see attached Fax Distribution list) sent with attached copy of a letter from the proponent dated March 4, 1998. | 1998/03/13 |
| re: Environmental Assessment of Jumbo Glacier Alpine Resort Project Letter from Raymond Crook of EAO sent to N J Purcell of White Rock BC regarding the duties of the Public Advisory Committee. | 1998/03/13 |
| Email from Raymond Crook of EAO sent to members of the Project Committee & other review agencies regarding timelines for the finalized revised version of the project report specifications. | 1998/03/13 |
| MEMO from Raymond Crook of EAO to the Project Committee membership (distribution list attached) sent with a copy of the February 18, 1998 correspondence from the proponent. | 1998/03/09 |
| re: Environmental Assessment of Proposed Jumbo Glacier Alpine Ski Resort Project Letter from Raymond Crook of EAO to Robert Madson of RK Heli-Ski Panorama Inc. in response to his letter faxed February 10, 1998 regarding concerns over the time being taken | 1998/03/04 |
| re: Environmental Assessment of the Jumbo Glacier Alpine Resort Project Letter from Raymond Crook of EAO to Chief Gayle Michel of the Columbia Lake Indian Band requesting the bands continued involvement in the above noted review. | 1998/03/02 |
| RE: Jumbo Glacier Alpine Resort Project Letter from Raymond L Crook of EAO to Roger Madson of R K Heli Ski Panorama Inc. in response to fax inquiry with regards to the draft project report specifications. | 1998/01/26 |
| Memo from Raymond L Crook of EAO to Jumbo Glacier Project Committee and Other Review Agencies with regards to additional correspondence from the proponent. | 1998/01/26 |
| Memo from Raymond L.Crook of EAO to Jumbo Glacier Project Committee and other Review Agencies regarding the proponent providing additional items of input and response to the first item of the January 13, 1998 letter. | 1998/01/23 |
| Fax from Roger Madson of R K Heli-Ski Panorama Inc to Ray Crook of EAO Fax requesting the status of the Jumbo Creek Resort Project. | 1998/01/23 |
| Letter from Ray Crook of EAO to the proponent regarding issues of meeeting with ministries and clarifying information, clarifying rough notes and a request for a written indication of facilities and activities that are not a part of the project for the PC. | 1998/01/19 |
| Letter from Raymond Crook of EAO to Oberto Oberti of Pheidias Project Management Corporation (Proponent) in response to the Proponents letter of December 4, 1997. | 1997/12/16 |
| Re: Environmental Assessment of the Proposed Jumbo Glacier Alpine Resort Project Letter from Raymond L. Crook of EAO to the proponent with regards to confirming the documentation which the proponent is intending to file for consideration. | 1997/12/05 |
| Email from Ray Crook of EAO to Jumbo Glacier Project Committee and other Review Agencies with regards to the proponent filing the list of documents in the follow-up to his September 15, 1997 letter and attachments. | 1997/12/05 |
| Letter from Sheila Wynn, DM of EAO to Betsy Telford of Salmo BC Letter sent on behalf of the Premier's office in response to Ms. Telford's letter of April 20, 1997 opposing the Jumbo project. (Telford's original letter attached) | 1997/12/02 |
| Letter from Sheila Wynn, DM of EAO to Vanessa Proulx of Spruce Grove AB Letter sent on behalf of the Premier's office in response to Ms. Prouix's letter of August 30, 1997 opposing the Jumbo project. (Prouix's original letter attached) | 1997/12/02 |
| Letter from Sheila Wynn, DM of EAO to Mona Gillespie of North Vancouver BC Letter sent on behalf of the Premier's office in response to Ms. Gillespie's letter of September 4, 1997 opposing the Jumbo project. (Gillespie's original letter attached) | 1997/12/02 |
| Letter from Sheila Wynn, DM of EAO to Lisa Snider of Hamilton ON Letter sent on behalf of the Premier's office in response to Ms. Snider's letter of November 1, 1997 opposing the Jumbo project. (Snider's original letter attached) | 1997/12/02 |
| Email from Raymond Crook of EAO to Jumbo Glacier Project Committee & Other Review Agencies Email advises of the postponement of the December 11/12 Project Committee Meeting. | 1997/11/27 |
| re: Proposed Jumbo Glacier Alpine Resort Project - Revised Minutes of February 26/27, 1997 Project Committee Meeting MEMO from Raymond Crook of EAO to the Project Committee Members and Other Review Agencies with copies of the above noted "revised" minutes | 1997/11/06 |
| subject: Jumbo Glacier Alpine Resort Project Email from Raymond Crook of EAO sent to the Project Committee & Other Review Agencies as an update on the draft project report specifications | 1997/11/06 |
| Re: Environmental Assessment Of Jumbo Glacier Alpine Resort Project Letter from Raymond L. Crook of EAO in response to Kenneth Parker's (Alpine Club of Canada) letter of September 30, 1997 regarding Jumbo Glacier Alpine Project. | 1997/10/21 |
| Letter from Sheila Wynn, Deputy Minister of EAO to Dr. Karen Hage, Leduc, Alberta. Letter in response to the Hage letter of September 3, 1997 regarding the Jumbo Glacier Project. (Original attached) | 1997/10/09 |
| Jumbo Glacier Project Proponent's Response to the Jumbo Glacier Alpine Resort Draft Project Report Specikfications and comments received on them dated September 29, 1997. | 1997/10/01 |
| Re: Jumbo Site Tour on September 18, 1997 Information on the Site tour on September 18, 1997. | 1997/09/22 |
| Subject: Jumbo Glacier Project Review E-mail from Raymond L. Crook of EAO to Dist. List Attached regarding various issues. | 1997/09/09 |
| Letter from Sheila Wynn, Deputy Minister of EAO to Sheila Haegeodorn, Victoria, BC. Letter in response to the Haegedorn letter of February 24, 1997 regarding the Jumbo Glacier Project. | 1997/09/03 |
| Letter from Sheila Wynn, Deputy Minister of EAO to Ross Priest, President, East Kootenay Hunter's Association Letter in response of the Priest letter of May 16, 1997 with regards to the Jumbo Glacier Project. (Original Attached) | 1997/07/28 |
| Re: Jumbo Glacier Alpine Resort Project Letter from Raymond Crook of EAO to the proponent with regards to copies of the public and public advisory committee documentation. | 1997/07/11 |
| Review of Public and Public Advisory Committee Input on Draft Project Report Specs. Memo from Raymond L. Crook of EAO to the Jumbo Glacier Project Committee and other Review Agencies. | 1997/07/07 |
| Re: Jumbo Glacier Alpine Resort Project Letter from Raymond L. Crook of EAO to the proponent with regards to the correspondence from Jim Carter, Chair of Jumbo Glacier project public advisory committee. | 1997/07/03 |
| E-mail from Raymond Crook of EAO to Jumbo Glacier Project Committee and Other Review Agencies with regards to receiving the advice and recommendations of the project public advisory committee on the draft report specifications. | 1997/06/30 |
| Letter from Ray Crook of EAO to Debra Hammer of Environmental Committee, Grant MacEwan Mountain Club Letter in response to the Hammer letter dated April 30, 1997 regarding the Jumbo Glacier Alpine Resort Project. | 1997/06/30 |
| Re: Jumbo Glacier Alpine Resort Project Letter from Raymond L. Crook of EAO in response to Roger Madson's (R. K. Heli-Ski Panorama Inc) fax of June 4, 1997 with regards to the public advisory committee minutes. | 1997/06/18 |
| subject: Jumbo Glacier Alpine Resort Project Email from Ray Crook of EAO to Members of the Jumbo project committee & other review agencies advising of a delay in finalising the public advisory committee's advice to the project committee. | 1997/06/10 |
| Response Letters from Raymond Crook of EAO to 6 addressees (attachments) Letters written on behalf of Premier Clark in response to 6 letters of comment/concern sent him. Original letters attached. | 1997/06/10 |
| Letter from Raymond Crook of EAO to Anja Etelamaki of Nelson BC Letter sent on behalf of Premier Clark in repsonse to a letter sent him (attached) dated April 20, 1997 from Anja Etelamaki. | 1997/06/10 |
| Letter from Raymond Crook of EAO to Marillyn McCombe of Nelson, BC Response letter to the McCombe letter of April 14, 1997 regarding the Jumbo Glacier Project. | 1997/06/02 |
| Letter from Raymond Crook of EAO to Inger Kronseth, Victoria,BC Letter in response to the Kronseth letters of February 4, 1997 and March 13, 1997 regarding the Jumob Alpine Ski Resort Project. | 1997/06/02 |
| Fax from Ray Crook of EAO to Roger Madson of R.K. Heli-Ski Fax in response of the May 6 and May 26 faxes with regards to the minutes of the Jumbo public advosory committee meetings. | 1997/06/02 |
| Letter from Raymond L Crook of EAO on behalf of the Premier to 6 addressees Letters respond to comments/concerns sent to Premier Clark. Original Letters to the Premier attached | 1997/05/29 |
| re: Jumbo Glacier Alpine Resort Project Memo from Tanya Howes of EAO to Derek Thompson, ADM of LUCO and Pia Archibald of MELP with attachment of May 6, 1997 letter from Oberto Oberti (proponent) to Raymond Crook of EAO on the issue development in the area | 1997/05/20 |
| Subject: Fwd: Acton Items from Jumbo PC Meeting Email from Raymond Crook of EAO to Jumbo Glacier Project Committee & other Review Agencies, with attached list of action items arising from the February 26/27, 1997 project committee meeting in Cranbrook. | 1997/03/20 |
| Letters from Raymond Crook of EAO to 27 addresses in response to correspondence sent Premier Clark with regards to the Jumbo Glacier Alpine Ski Resort. | 1997/03/17 |
| Letter from Raymond Crook of EAO to Robert Campsall of the Jumbo Creek Conservation Society Letter in response to letter sent by Mr. Campsall to the Premier regarding concerns with the proposed Jumbo Glacier Alpine Resort project. | 1997/03/11 |
| Letter from Sheila Wynn of EAO to Sheila Haegedorn of Victoria BC Letter responding to Haegedorn's letter of February 12, 1997, advising that it will be forwarded to Raymond Crook of EAO. | 1997/02/20 |
| Next (February 26/27, 1997) Project Committee Meeting Cover letter sent by Raymond Crook of EAO to Project Committee members with attachments. | 1997/02/11 |
| Review of Proposed Jumbo Glacier Alpine Resort Project - Project Committee Fourth EA Meeting - Proposed Agenda As noted above, Agenda of Meeting to be held Feburary 26 & 27 in Cranbrook BC. | 1997/02/10 |
| Letter from Raymond Crook of EAO to Peter Wood of Selkirk College - Nelson Campus Tourism Program to sit on the above noted Committee reviewing the Jumbo project. | 1997/02/06 |
| subject: Jumbo Glacier Resort Project Email from Raymond Crook of EAO to the Jumbo Glacier Project Committee and Other Review Agencies to advise of the status of the Public Advisory Committee. | 1997/01/30 |
| Email from Bob Jamieson to Raymond Crook of EAO regarding various issues regarding public participation and technical issues of the proposal. Attached response from Raymond Crook. | 1997/01/30 |
| Email from Raymond Crook of EAO to Jumbo Glacier Project Committee and Other Review Agencies to advise of issues for the upcoming Project Committee meeting on February 27, 1997. | 1997/01/21 |
| E-mail to Project Committee & other review agencies re Jumbo Glacier Alpine Resort Project | 1997/01/17 |
| Email from Raymond Crook of EAO to the PRC & other review agencies regarding his vacation & Leslie Hildebrandt of EAO as contact in his absence as well as noting the upcoming first meeting of the PAC. | 1997/01/08 |
| Memo from Raymond Crook of EAO to PRC members (list attached) with copy of letter & attachment from Proponent dated December 18, 1996 re: article in Ski Canada magazine titled "Jumbo Dreams". (article attached) | 1997/01/08 |
| Letter from Raymond Crook of EAO to R. Steckle of the East Kootenay Community College acknowledging receipt of his letter of December 10, 1996 regarding participation on the PAC. | 1996/12/27 |
| Letter from Raymond Crook of the EAO to Dave Milne of Milne Consulting, in response to his letter of September 6, 1996 regarding facilitation services. | 1996/12/27 |
| Reivew of Proposed Jumbo Glacier Alpine Resort Project Assessment of the adequacy of measures being implemented for Public and First Nations notification, Access to Information and consultation. Prepared by the EAO. | 1996/12/18 |
| Public Advisory Committee (PAC) - TOR First Draft of the operating procedures (terms of reference) for the PAC for the Jumbo Glacier project review. | 1996/12/18 |
| Memo from Raymond Crook of EAO to Members of the Jumbo Glacier Project Committee & Other review agencies sent as cover with copies of the Draft Specs. | 1996/12/18 |
| Public Advisory Committee - First Meeting, Tuesday January 14, 1997 - Cranbrook BC Draft of a Proposed Agenda sent to members of the Public Advisory Committee for the Jumbo Glacier Resort project. | 1996/12/18 |
| Letter from Raymond Crook to Main & alternate members of the Jumbo Glacier Project Public Advisory Committee sent in addition to the draft proposed agenda to the first PAC meeting. | 1996/12/18 |
| Email to the Jumbo Glacier Project Committee & Other Review Agencies advising them that the proposed "release & response" schedule for the draft specifications report | 1996/12/18 |
| Letter from Raymond Crook of EAO to Oberto Oberti sent as cover to the draft specifications report. | 1996/12/18 |
| Project Review Letter from Tanya Howes of EAO to Roger Madson of R.K. Heli-Ski Panorama Inc. regarding the resumption of the Jumbo Review, beginning with a Project Committee Meeting in Cranbrook on February 26 | 1996/12/17 |
| Memo from Tanya Howes to the Public Advisory Committee regarding the scheculing of their first meeting to review Draft Project Report Specifications for the EA of the proposed Jumbo Project. | 1996/12/13 |
| Draft Project Report Specifications (or terms of reference) for the Project Report that Pheidias must file in support of its application for the Jumbo project. | 1996/12/13 |
| Extension of time order #1 (407 days) and Extension of time order #2 (485 days) | 1996/11/29 |
| Re: Jumbo Glacier Alpine Resort Fax from Raymond Crook to the Project Committee with attached copy of Proponent suggested changes to the Project Committee Meeting Minutes of August 2, 1995. | 1996/11/07 |
| Letter to Roger Madson of RK Heli-Ski Panorama Inc, in response to his letter of September 10, 1996 regarding the "delay" in the project review. | 1996/09/30 |
| Memo from Raymond Crook to Bill Irwin & Bryan Gates of MELP as cover to 2 forwarded letters received. | 1996/09/30 |
| Letter to Roger Madson, RK Helli-Ski re: Jumbo | 1996/09/18 |
| Letter from Ray Crook of EAO to Oberto Oberti of Pheidias Project Management Corporation. Re: Response to Aug. 1, 1996 letter raising concerns. | 1996/08/16 |
| Your July 30, 1996 FOI Request to BC Lands, MELP, with Respect to the Proposed Jumbo Glacier Alpine Resort Proposal Letter from Ray Crook of EAO to Sarah Coulter. Re: Response to FOI request regarding provincial ministry involvement in the review. | 1996/08/15 |
| Environmental Impacts of Skiing Letter from Ray Crook of EAO to proponent. Re: Forwarding of paper titled "The Impacts of Skiing on the Environment - Opportunities for Action". | 1996/08/12 |
| Jumbo Project Draft Specifications Email from Ray Crook of EAO to Project Committee members and Review Agencies. Re: Informing that latest draft of specifications has been completed and will be forwarded for review. | 1996/08/08 |
| Jumbo Glacier Alpine Resort Project Email to the Project Committee & Other Review Agencies regarding the mailing of the draft project specifications in mid July. | 1996/07/08 |
| Letter from Raymond Crook to all members & alternates of the Jumbo PAC, notifying them that he is still not in a position to schedule the first PAC meeting. | 1996/07/02 |
| Letter from Ray Crook of EAO to Eric Schindler of Pro Terra Kootenay Nature Allies. Re: Response to May 16, 1996 letter. | 1996/06/05 |
| Email from Ray Crook of EAO to Russ Haas of Invermere Forest District. Re: Response to May 7, 1996 email. | 1996/05/30 |
| Letter from Martyn Glassman of EAO to Alan Artibise. Re: Forwarding of examples of TOR of traditional use studies and a copy of the study done by Bjorn Simonsen of the Bastion Group on the Crystal Peak | 1996/05/30 |
| Fax from Ray Crook of EAO to Roger Madson of RK Heli-Ski Panorama Inc. Re: Awaiting advice from MELP with respect to project report specifications for grizzly bear studies. | 1996/05/30 |
| Letter from Ray Crook of EAO to Chief Paul Sam of Shuswap Indian Band. Re: Forwarding of letter from Oberto Oberti of PPMC regarding changes to draft minutes of Nov. 22, 1995 project committee meeting. | 1996/05/04 |
| EA Review of the Proposed Jumbo Glacier Resort Project Letter from Ray Crook of EAO to Oberto Oberti of PPMC. Re: Changes to draft minutes of November 22, 1995 Project Committee meeting. | 1996/05/04 |
| Jumbo Glacier Alpine Resort Proposal Letter from Ray Crook of EAO to Roger Madson of R.K. Heli-Ski Panorama Inc. Re: Unable to schedule presentation to project committee before draft project report specs are readied for public review and comment. | 1996/04/09 |
| Fax from Ray Crook of EAO to Public Advisory Committee Members Re: Unable to schedule first meeting of public advisory committee until completion of draft project report specs. | 1996/04/09 |
| Presentation on EA Process to Ktunaxa/Kinbasket Communities. Speaking notes for March 26, 1996 presentation at St. Mary's Reserve, Cranbrook, BC. | 1996/04/01 |
| East Kootenay CORE Plan | 1996/03/26 |
| Comments on Project Committee Report on Jumbo | 1996/03/22 |
| RE: Draft assessment of public notification, access to information and consultation measures for Jumbo Glacier project application review | 1996/03/20 |
| Fax: Comments on Public and First Nations Notification | 1996/03/19 |
| Fax: Jumbo Glacier Project | 1996/03/15 |
| Jumbo Glacier Resort Proposal Email from Ray Crook of EAO to Jumbo Glacier Project Committee and Other Review Agencies. Re: Missing pages in document mailed under cover of February 9, 1996 memo. | 1996/03/04 |
| Fax from Ray Crook of EAO to Project Committee Members/Other Review Contacts Re: Forwarding cover letter for various documents circulated by mail with update on the status of the review. | 1996/02/16 |
| Fax from Ray Crook of EAO to Public Advisory Committee Members Re: Advising PAC members that the first PAC meeting has been scheduled for February 15, 1996. Draft Agenda attached. | 1996/02/14 |
| Letter from Ray Crook of EAO to Larry Greenlaw of Regional District of Central Kootenay. Re: Forwarding minutes of August 2, October 18, and November 22, 1995 project committee meetings. | 1996/02/14 |
| Proposal Letter from Ray Crook of EAO to Oberto Oberti of Pheidias Project Management Corporation. Re: Forwarding of copy of draft minutes of the November 22, 1995 project committee meeting. | 1996/02/14 |
| Fax from Ray Crook of EAO to Public Advisory Committee Members Re: Notice of postponement of February 15, 1996 PAC meeting. | 1996/02/14 |
| Jumbo Glacier Project - Public Advisory Committee (PAC) Letter from Raymond Crook to Randal McRoberts in response to his letter of January 5, 1996. Questions were related to the issue of the Public Advisory Committee. | 1996/02/08 |
| Letter from Raymond Crook to Roger Madson of R.K. Heliski Panorama Inc. in response to his letters of January 10 & 26, 1996 which raised concerns over the timelines of the review and participation on the Public Advisory Committee. | 1996/02/08 |
| Proposed Jumbo Glacier Alpine Resort Project Committee 3rd EA Meeting Agenda Revised Agenda for 3rd EA Meeting held on November 22, 1995 in Cranbrook | 1996/02/08 |
| Proposed Jumbo Glacier Alpine Resort Project - Project Committee Third EA Meeting November 22, 1995, Cranbrook. Provisional Meeting Minutes. | 1996/02/08 |
| Letter from Raymond Crook to the Proponent in response to the 8 points surrounding Public Misinformation raised in their December 18, 1996 letter. | 1996/02/07 |
| Proposed Jumbo Glacier Alpine Resort Project Committee Second EA Meeting - October 18, 1995 - Revised Minutes. | 1996/01/31 |
| Re: Review of Jumbo Glacier Alpine Ski Resort Project Memo from Raymond Crook to Gary Paget of Municipal Affairs Ministry with attachment of document #525 - Letter from Regional District of East Kootenay. | 1996/01/31 |
| Fax with Letter re: Review of the Proposed Jumbo Glacier Alpine Resort Project Under the Environmental Assessment Act - Public Advisory Committee - Public Advisory Committee Membership List etc. | 1996/01/31 |
| Subject re: Environmental Assessment/Jumbo | 1996/01/25 |
| Establishment of a Public Advisory Committee Letter to Groups invited to be members of the Public Advisory Committee (PAC) with a distribution list. | 1996/01/11 |
| Letter from Raymond Crook to Roger Madson of R.K. Heli-Ski Panorama Inc. in response to his letters raising issues with respect to the implications of the Jumbo Glacier resort proposal on his company. | 1996/01/11 |
| Letter from Raymond Crook to Marilyn James & Robert Watt of Sinixt/Arrow Lakes Nation in response to their letter involving First Nations Interests & Rights. | 1996/01/11 |
| Letter from Raymond Crook to Larry Greenlaw of Regional District of Central Kootenay confirming his appointment as representative on the Jumbo Glacier Project Committee. | 1996/01/11 |
| re: Jumbo Glacier Resort Project Review | 1996/01/11 |
| Email to the Project Review Committee with information update on the Draft Project Report Specifications and the Public Advisory Committee. | 1995/12/14 |
| Project Committee First EA Meeting - August 2, 1995 Minutes of the First EA Meeting on August 2, 1995 in Cranbrook BC - Finalized Minutes accepted by project committee with minor changes. | 1995/12/12 |
| Environmental Assessment Act - Public Advisory Committees - Terms of Reference of the Public Advisory Committee (PAC) - Activities of the PAC - Whether or Not to Establish a PAC - Commencement and Conclusion of PAC Operations etc. | 1995/12/12 |
| Jumbo Glacier Environmental Assessment Public Meeting - Invermere, 7:00pm to 11:30pm, September 14, 1995 Issues paper created after the public meeting in Invermere on Septebmer 14, 1995 with regards to the Jumbo Project. | 1995/12/12 |
| Jumbo Glacier Environmental Assessment Public Meeting - Nelson, September 20, 1995 Issues sheet created after the Nelson Public Meeting of September 20, 1995 with regards to the Jumbo Project. | 1995/12/12 |
| FAX to Project Committee with suggested Lead Agencies assigned to coordinate the Project Report Specifications for each Topic | 1995/12/06 |
| Faxes sent to Respresentatives of the Public Advisory Committee (PAC) with an attached copy of the First Draft of the PAC Terms of Reference Document See Draft TOR for Public Advisory Committee. | 1995/12/01 |
| Email message as summary of Key Action items from the November 22, 1995 Project Committee Meeting in Cranbrook. | 1995/12/01 |
| Re: Question Email from Raymond Crook to Alaistari Fraser with a rough count of the number of public responses that are stating; supporting, opposing and unknown positions regarding the Jumbo Project. | 1995/11/27 |
| Jumbo Glacier Project Committee & Other Review Agencies Email from Raymond Crook to Project Committee Members regarding the upcoming meeting of November 22, 1995 in Cranbrook. | 1995/11/16 |
| Jumbo Glacier Resort Project - Project Committee Membership & Other Committee Contacts - November 16, 1995 Update Updated listing of all Project Committee Members by their Agency Grouping; Federal, Provincial, First Nations, Local/Municipal Governments. | 1995/11/16 |
| Email sent to the Project Committee requesting additional feedback to complete a first draft of the project report specifications by November 22, 1995 project committee meeting in Cranbrook. | 1995/10/31 |
| Memo from Raymond Crook to the Project Committee members who had been unable to attend the October 18, 1995 meeting. Attached are 11 documents that had been given out at the committee meeting. | 1995/10/26 |
| Project Committee Membership & Other Committee Contacts List of Project Committee Contacts by Agency grouping; Provincial, Federal, First Nation & Local/Municipal Governments | 1995/10/26 |
| Review of Proposed Jumbo Glacier Alpine Resort - Project Committee - Second EA Meeting October 18, 1995. | 1995/10/20 |
| Provisional Minutes of Project Committee Meeting in Windermere on October 18, 1995. | 1995/10/20 |
| Email from Raymond Crook to Project Committee regarding the upcoming minutes of October 18, 1995 meeting. | 1995/10/20 |
| Jumbo Glacier Resort Project Review Email from Raymond Crook to Project Committee regarding the preperation of the October 18, 1995 meeting minutes and summarizing the key action items arising from the meeting. | 1995/10/20 |
| Views Expressed & Issues Identified by the Public with respect to the Jumbo Glacier Alpine Resort Project - October 17,1995 - Draft issues listing of public views & concerns. | 1995/10/18 |
| Project Committee & Other Review Contacts Email from Raymond Crook to Project Committee with a proposed agenda for the October 18, 1995 Project Review Committee Meeting. | 1995/10/13 |
| Letter sent by Raymond Crook of EAO to Hans Cunningham Chair of the Regional District of Central Kootenay inviting participation by the District on the Project Committee. | 1995/10/12 |
| Email from Raymond Crook to the Project Committee to confirm the set up of the next Project Committee Meeting - October 18, 1995. | 1995/10/12 |
| Letter from Raymond Crook to Hans Cunningham of Regional District of Central Kootenay inviting a respresentative to sit on the Project Reivew Committee. | 1995/10/12 |
| Subject: Jumbo Glacier Project Review - Nelson Public Meeting Sept. 20 Email from Raymond Crook to George McKay regarding the proposed Nelson Public Meeting. | 1995/09/25 |
| Speaking Notes for Public Meeting - Jumbo Glacier Project Review September 14, 1995 Copy of Speaking Notes given by Raymond Crook at the September 14, 1995 in Invermere. | 1995/09/19 |
| Email from Raymond Crook to Project Review Committee regarding the September 20, 1995 site tour schedule. | 1995/09/18 |
| Email from Raymond Crook to the Project Review Committee regarding the public meeting on September 20, 1995 in Nelson | 1995/09/18 |
| Email from Raymond Crook to Project Review Committee regarding public consultation & open-house sessions with regard to the Jumbo project. | 1995/09/12 |
| Letter sent from Martyn Glassman to Paul Scott regarding the non participation of the Department of Indian Affairs and Northern Development in the Jumbo Glacier Project Review. | 1995/08/24 |
| Letter from Raymond Crook in response to a letter from Inger Kronseth explaining the EA Review Process and public consultation/involvement. | 1995/08/21 |
| Letter from Raymond Crook to R.K. Heli-Ski Panorama Inc. regarding their concerns over the Jumbo Creek Project and implications for their existing heli-skiing operations. | 1995/08/21 |
| Letter from Raymond Crook requesting prior correspondence from R. Eloise be resent for inclusion in the review of the Jumbo Creek Project. | 1995/08/21 |
| Email from Raymond Crook to the Project Review Committee listing Martyn Glassman as his back-up while on vacation and reminding the committee of the proposed site tour set for September 14, 1995. | 1995/08/21 |
| Email message to the Project Review members and other involved agencies within government as an update on the status of the review process for the Jumbo Glacier Alpine Resort project. | 1995/08/12 |
| Letter to Oberto Oberti acknowledging receipt of the application for a project approval certificate for the Jumbo Glacier Alpine Resort Project, and informing of a transition Order for the Project. | 1995/08/09 |
| Copy of Revised Agenda for the First EA Meeting for the Review of the proposed Jumbo Glacier Alpine Resort Project on August 2, 1995. | 1995/08/01 |
| Copy of Guidelines for Review Comments sent to the Project Committee with regards to the Review of the Jumbo Glacier Alpine Resort Proposal. | 1995/08/01 |
| Minutes of Meeting on Environmental Assessment Process - for Jumbo Creek Resort Project. | 1995/08/01 |
| Copies of all letters sent to potential Project Committee Review Members outlining the change of Directors from Derek Griffin to Raymond L. Crook. | 1995/07/21 |
|