South Fraser Perimeter Road Project

Type:Typical EA Process (Active and Complete)Status:Completed / Certified
Category:TransportationPre-application

Start Date:

2003/02/03

Pre-Application EAO Generated Documents



Folder

Date Posted

Meeting Summary Notes dated Mar. 8/06 from the Tenth Pre-application Meeting for the South Fraser Perimeter Road Project 2006/04/04
Meeting Summary Notes dated Aug. 17/05 from the Ninth Pre-application Meeting for the South Fraser Perimeter Road Project 2005/10/31
Reply letter dated Sept. 7/05 from Jan Hagen (EAO) to Verne Kucy (Corporation of Delta) regarding the Environmental Assessment of the South Fraser Perimeter Road 2005/09/07
Meeting Summary Notes dated May 18/05 from the Eighth Pre-application Meeting for the South Fraser Perimeter Road Project2005/08/12
Letter dated May 25/05 from Jan Hagen (EAO) to Gillian Anderson (BC Great Blue Heron Society) in response to a Feb. 28/05 email/letter regarding the Gateway South Delta Project2005/05/31
Email dated Feb. 28/05 from Jan Hagen (EAO) to Mary J. Taitt (Boundary Bay Conservation Committee) acknowledging receipt of a Feb. 28/05 letter regarding the South Fraser Perimeter Road, Delta Segment Community Consultation2005/05/25
Meeting Summary Notes dated Feb. 22/05 from the Seventh Pre-application Meeting for the South Fraser Perimeter Road Project 2005/05/03
Final Minutes dated Oct. 27/04 from the Sixth Pre-application Meeting for the South Fraser Perimeter Road Project 2005/01/21
Order under Section 11 of the Environmental Assessment Act signed by Jan E. Hagen (EAO) and dated Oct. 21/04 2004/10/22
Final Minutes dated August 26/04 from the Fifth Pre-application Meeting for the South Fraser Perimeter Road Project 2004/09/15
Final Minutes dated April 16/04 from the Fourth Pre-application Meeting for the South Fraser Perimeter Road Project2004/05/12
Final Minutes dated March 31/04 from the Third Pre-application Meeting for the South Fraser Perimeter Road Project2004/04/29
Final Minutes dated March 22/04 from the Second Pre-application Meeting for the South Fraser Perimeter Road Project2004/04/06
Final Minutes dated Feb. 20/04 from the First Pre-application Meeting for the South Fraser Perimeter Road Project2004/03/09
Letter dated Feb. 16/04 from Joan Hesketh (EAO) to Robin Taylor (MOT) regarding the South Fraser Perimeter Road, Request for Re-Scoping of the Pre-Application2004/02/17
Letter dated Dec 9/02 from Ray Crook (EAO) to George V Harvie (The Corporation of Delta) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment review2003/05/06
Letter dated Dec 9/02 from Ray Crook (EAO) to Hugh Kellas (GVRD) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Letter dated Dec 9/02 from Ray Crook (EAO) to Umendra Mital (City of Surrey) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Steve Acheson (MSRM) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Gord Enemark (CSE) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Carl Alleyne (Health Canada) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Andrew Robinson (Canadian Wildlife Service) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Brian Clark (MWLAP) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Elaine Taylor (MCAWS) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Adrian Duncan (Environment Canada) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Jack Smith (Environment Canada) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Linda Sullivan (CEAA) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Herb Klassen (DFO) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the environmental assessment process2003/05/06
Memo dated Dec 19/02 from Ray Crook (EAO) to Steve Martin (Fraser Health Authority) regarding the proposed South Fraser Highway Project - Invitation to participate in the envrionmental assessment process2003/05/06
Letter dated Dec 23/02 from Ray Crook (EAO) to Chief and Council (Tsawwassen First Nation) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the EA Process2003/05/01
Letter dated Dec 23/02 from Ray Crook (EAO) to Chief and Council (Kwayhquitlum First Nation) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the EA process2003/05/01
Letter dated Dec 23/02 from Ray Crook (EAO) to Chief and Council (Kwantlen First Nation) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the EA process2003/05/01
Letter dated Dec 23/02 from Ray Crook (EAO) to Chief and Council (New Westminister Indian Band) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the EA process2003/05/01
Letter dated Dec 23/02 from Ray Crook (EAO) to Chief and Council (Musqueam Indian Band) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the EA process2003/05/01
Letter dated Dec 23/02 from Ray Crook (EAO) to Chief and Council (Semiahmoo First Nation) regarding the proposed South Fraser Perimeter Highway Project - Invititation to participate in the EA Process2003/05/01
Letter dated Dec 23/02 from Ray Crook (EAO) to Chief and Council (Sto:lo Nation) regarding the proposed South Fraser Perimeter Highway Project -Invitation to participate in the EA process2003/05/01
Letter dated Dec 23/02 from Ray Crook (EAO) to Cheif and Council (Katzie First Nation) regarding the proposed South Fraser Perimeter Highway Project - Invitation to participate in the EA process2003/05/01
Meeting Minutes dated Mar 13/03 - Pre-Application Meeting - Joint Socio-economic Community/Biophysical Technical Working Group2003/04/07
Pre-Application meeting minutes from December 3 2002 held in Victoria regarding the South Fraser Perimeter Highway Project2003/02/27
Pre-Application meeting minutes from January 29 2003 regarding the South Fraser Perimeter Highway Project2003/02/27
Letter dated Jan 27/03 from Ray Crook (EAO) to Clive Rock (Greater Vancouver Transportation Authority) regarding the upcoming BTWG and SCWG meetings planned for Jan 29/032003/02/03
Order Under Section 10(1)(c) dated Feb 3/03 signed by Ray Crook2003/02/03
Last Updated: 2009-11-21