New Fraser River Crossing Project

Type:Typical EA Process (Active and Complete)Status:Completed / Certified
Category:Water ManagementPre-application

Start Date:

2003/03/18

Under Review EAO Generated Documents



Folder

Date Posted

Time Limit Extension Order for the New Fraser River Crossing Project dated July 28/042004/07/28
Letter dated June 7/04 from Ray Crook (EAO) to Fred Cummings (TransLink) regarding restarting the 180-days legislated time limit2004/06/07
Letter dated Mar 30/04 from Derek Griffin (EAO) to Chief Peter James (Katzie First Nation) response to Katzie's letter of Mar 12/042004/03/31
Letter dated Mar 26/04 from Derek Griffin (EAO) to Fred Cummings (TransLink) regarding the New Fraser River Crossing Project - Suspention of time limit for the review of the applicaiton2004/03/29
Letter dated Feb 25/04 from Derek Griffin (EAO) to Fred Cummings (TransLink) re: Lifting the suspension of the time limit for the review of your application.2004/02/27
Letter dated Feb 02/04 from Derek Griffin (EAO) to Fred Cummings (TransLink) re: Response to Fred's letter requesting an extension2004/02/03
Minutes - New Fraser River Crossing Biophysical Working Group Meeting Jan 13/04 2004/01/22
Minutes - New Fraser River Crossing Socio-Economic Working Group Meeting Jan 13/042004/01/22
Second Order Under Section 13 Amending Section 11 Order2003/12/04
Letter dated Nov 26/03 from Ray Crook (EAO) to Fred Cummings (TransLink) re: New Fraser River Crossing Project - Second Amendment of Section 11 Order2003/12/04
Letter dated Nov 28/03 from Ray Crook (EAO) to Fred Cummings (TransLink) re: Acknowledgement of Receipt and Acceptance for Formal Detailed Review of the Application Supplement 2003/12/03
Memo dated Dec 2/03 from Ray Crook (EAO) to Socio-economic and Biophysical/Technical Working Group Members - New Fraser River Crossing Project Application Supplement Review Process2003/12/03
Minutes - New Fraser River Crossing Working Group Meeting October 21/032003/11/20
Order Under Section 132003/11/19
Issues Tracking Chart - Updated Oct 8/032003/10/29
Letter dated Oct 3/03 from Ray Crook (EAO) to Fred Cummings (TransLink) regarding the New Fraser River Crossing Project - Request to Use Various Means to Advertise Open Houses/Public Meetings with Section 13 Order2003/10/06
Last Updated: 2009-11-21