Galore Creek Copper-Gold-Silver Project

Type:Typical EA Process (Active and Complete)Status:Completed / Certified
Category:MiningPre-application

Start Date:

2004/02/25

Pre-Application EAO Generated Documents



Folder

Date Posted

Letter dated June 14, 2006 from Anne Currie (EAO) to Sue Craig and Carl Gagnier (NovaGold) accepting the application for the Galore Creek Copper-Gold-Silver Project for formal review.2006/06/15
Letter dated June 14, 2006 from Anne Currie (EAO)to Carl Gagnier and Sue Craig (NovaGold) re: Assessment of Public and First Nations Consultation Programs.2006/06/15
Order making second amendment to section 11 order, dated June 13/06 and signed by Anne Currie (EAO) 2006/06/14
Letter dated March 10/06 from Anne Currie (EAO) to Sue Craig and Carl Gagnier (NovaGold Canada Inc.) accepting the Approved Terms of Reference for the Galore Creek Copper-Gold-Silver Project2006/03/10
Order under Section 13, amending section 11 order, dated March 7/06 and signed by Anne Currie(EAO)2006/03/07
Order Under Section 11 issued on November 30, 2005 by Anne Currie (EAO) for the Galore Creek Copper-Gold-Silver Project2005/12/01
Galore Creek Silver/Copper/Gold Project Meeting Final Notes September 23, 20042004/11/15
Galore Creek Copper/Gold Project Meeting Final Notes July 28/04 - Dease Lake Community Hall2004/10/06
Galore Creek Copper/Gold Project Meeting Final Notes - June 29, 20042004/08/17
Letter dated July 8, 2004 to District of Stewart re: Mining Project under Review by British Columbia signed by both Garry Alexander and Anne Currie2004/07/08
Proposed Galore Creek Gold/Silver/Copper Project Final Meeting Notes - May 13/04 2004/06/22
Proposed Galore Creek Gold/Silver/Copper Project Final Meeting Notes - April 5-6/042004/06/09
Galore Creek Gold-Silver-Copper Project - Order under Section 10(1)(c) dated Feb 25/04 and signed by Anne Currie (EAO)2004/02/27