Galore Creek Copper-Gold-Silver Project

Type:Typical EA Process (Active and Complete)Status:Completed / Certified
Category:MiningPre-application

Start Date:

2004/02/25

Under Review Application and Supporting Studies



Folder

Date Posted

Diffuser Installation for Trenching Report dated Dec 13/06 from Dianna Stoopnikoff (NovaGold) to Anne Currie (EAO).2006/12/18
Interior Grizzly Bear Cumulative Effects Assessment Report - November 2006 - Prepared by Rescan Environmental Services and Rescan Tahltan Environmental Consultants2006/12/08
Post Closure Long-Term Water Quality Predictions (without mitigation) dated November 20062006/12/08
Revised Tunnel Alignment and Related Geotechnical Investigations Report dated November 2006 submitted by NovaGold2006/11/20
Report dated Nov 14/06 from Dianna Stoopnikoff (NovaGold) to Anne Currie (EAO) regarding the Tailings Dam Geologic Condition for the proposed Galore Creek Copper-Gold-Silver Project.2006/11/17
Letter dated Nov 2/2006 from Dianna Stoopnikoff (Novagold Inc) to Anne Currie (EAO) regarding Galore Creek EA Application Additional Information: Changes to Construction Camps2006/11/03
Report dated Sept 22/06 from Iain G. Bruce (BGC Engineering Inc.) to Dean Lindsay (NovaGold) regarding the Galore Creek Project- Plant Site Design - Feasibility Geotechnical Report2006/10/24
Report dated Sept 26/06 from Dianna Stoopnikoff (NovaGold) to Anne Currie (EAO) regarding the Overland Pipelines Detailed Feasibility Study by PSI.2006/10/02
Report dated Jul 31/06 from Iain G. Bruce (BGC Engineering Inc.) to Dean Lindsay (NovaGold) regarding the Galore Creek Project- Open Pit Slope Design.2006/10/02
Report dated Sept 7/06 from Dianna Stoopnikoff (NovaGold) to Anne Currie (EAO) regarding the Human Health Effects Assessment.2006/09/11
Report dated Sept 7/06 from Dianna Stoopnikoff (NovaGold) to Anne Currie (EAO) regarding the Porcupine River Floodplain Declineation near the Proposed Aerodrome Facility.2006/09/11
Report dated Sept 7/06 from Dianna Stoopnikoff (NovaGold) to Anne Currie (EAO) regarding the Water Quality Model Predictions Total and Dissolved Metals.2006/09/11
Email dated Aug 17/06 from Dianna Stoopnikoff (NovaGold) to Nicole Vinette (EAO) regarding the change in location of the filter plant for the proposed Galore Creek Project. 2006/08/18
Volume 1 - Main Document - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 2 - Main Document - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 3 - Main Document - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 4 - Appendix 1 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 5 - Appendix 2 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 6 - Appendix 3 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 7 - Appendix 4 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 8 - Appendix 5 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 9 - Appendix 6 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 10 - Appendix 7 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 11 - Appendix 8 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 12 - Appendix 9 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 13 - Appendix 10 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 14 - Appendix 11 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 15 - Appendix 12 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Executive Summary - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Volume 16 - Appendix 13 - Application for an Environmental Assessment Certificate for the Galore Creek Project submitted by Novagold Canada Inc to Anne Currie (EAO) June 2006.2006/06/26
Last Updated: 2009-11-21