Folder | Date Posted |
| Memo from Lee Thiessen, MEMP to Reviewers regarding the review and comments on enclosed "Introduction to the Installation of Unit 5 at Revelstoke Generating Station | Unknown |
| Letter from Shirley Boon, Ministry of Government Services to Lee Thiessen, MEMP stating that they we unable to comment on a complete procurement plan at this time | Unknown |
| Letter from Dean Handley, MoTH to Lee Thiessen, MEMP regarding their concerns about no downstream concerns above the Revelstoke Dam | Unknown |
| Letter from John Philion (MoH) to Lee Thiessen (MEMP) regarding the receipt of the "Introduction to the Installation of Unit 5 at Revelstoke Generating Station | Unknown |
| Letter from Derek Griffin (MEI) to Lee Theissen (MEMP) from regarding the review of the prospectus | Unknown |
| Letter from Ray Kenny (MSBTC) to Lee Thiessen (MEMP) regarding the completion of the review of "Introduction to the Installation of Unit 5 at Revelstoke Generation Station | Unknown |
| Memo from Janet Fontaine (MEMP) to Lee Thiessen (MEMP) regarding "Introduction for Installation of Unit 5 - Revelstoke Generating Station and Unit 4 - Seven Mile Generating Station | Unknown |
| Letter from Lee Thiessen (MEMP) to Walter Udel, BC Hydro regarding the selected government agencies and other stakeholders that have reviewed the Introduction for Installation of Unit 5 | Unknown |
| Memo from Doug Dryden (Ministry of Environment) to Lee Thiessen (Ministry of EMP) regarding their comments on the "Introduction" document which include water, fisheries, lands and parks. | Unknown |
| Letter from Ray Ghosh, Ministry of Municipal Affairs to Lee Thiessen, Ministry of E,M&P regarding the "Introduction" report | Unknown |
| Letter from NCJ Smith, BC Utilities to Lee Thiessen, Ministry of E,M&P regarding the "Introduction" document, they have reviewed and have no comments on its contents | Unknown |
| Memo from Doug Dryden, Ministry of Environment to Lee Thiessen, Ministry of E,M&P regarding the "Evaluation of the Introduction" document | Unknown |
| Memo from Paul Wieringa, Ministry of E,M&P to selected reviewers regarding "Evaluation of the Introduction" requesting reviews and comments on quality, accuracy and completeness | Unknown |
| Letter from Dave Grieve, Ministry of E,M&P to Paul Wieringa, Ministry of E,M&P requesting a copy of the Revelstoke evaluation to review and comment | Unknown |
| Memo from John Philion, Ministry of Health to Paul Wieringa, Ministry of E,M&P regarding the project has been reviewed and found that there would be no consequences from construction | Unknown |
| Memo from Derek Griffin, Ministry of Employment and Investment to Denise Mullen-Dalmer, Ministry of E,M&P regarding thier review of the Evaluation report | Unknown |
| Memo from Jim Blake, Ministry of Forests to Paul Wieringa, Ministry of E,M&P regarding the review | Unknown |
| Letter from K.B. Miller, Provincial Agricultural Land Commission to Paul Wieringa, Ministry of E,M&P regarding the evaluation | Unknown |
| Letter from N.C.J. Smith, BC Utiltiies Commission to Denise Mullen-Dalmer, Ministry of E,M&P stating that they have no concerns of the project justification. | Unknown |
| Letter from Ray Ghosh, Ministry of Municipal Affairs to Paul Wieringa, Ministry of E,M&P regarding the socio-economic impact study that there may be an impact on the Tourism | Unknown |
| Letter from D.P. Handley, MoTH to Paul Wieringa, MEMP regarding a concern of the increased scour affecting the downstream bridges | Unknown |
| Letter from Ray Kenny, Ministry of Small Business, Tourism and Culture to Paul Wieringa, Ministry of E,M&P regarding the Archaeology Branch has not identified any potential impacts | Unknown |
| Letter from Denise Mullen-Dalmer, Ministry of E,M&P to Walter Udell, BC Hydro regarding the evaluation, a list of correspondence received attached. | Unknown |
| Memo from R.J. Hammond, Ministry of Environment to Rick Morley, Ministry of Environment regarding entrainment, zero discharge, reservoir fluctuations and increased water velocities/elevations below dam. | Unknown |
| Memo from Denise Mullen-Dalmer, Ministry of E,M&P to selected reviewers regarding the attached BC Hydro's consolidated reponses to the Summary of Review Comments. | Unknown |
| Memo regarding Fish & Aquatic Issues and attachment "Cumulative Impact Assessment" prepared for BC Hydro by Triton, Environmental Consultants Ltd. | Unknown |
| Letter from Jon O'Riordan, Ministry of Environment to T.M. Thompson, BC Hydro regarding a possible delay of the project would allow more time to finalize plans, conduct studies and refine prior designs of construction. | Unknown |
| Letter from G.R. Powell, Ministry of Small Business, Tourism and Culture to Derek Griffin regarding that the Archaeology Branch has not identified any potential impact on archaeology sites | Unknown |
| Memo from David Raven, Ministry of Forest to Derek Griffin stating that their original comments have not changed or have any additional concerns. | Unknown |
| Memo from Ray Ghosh, Ministry of Municipal Affairs to Derek Griffin regarding the City of Revelstoke and BC Hydro's negotiations for mitigation and compensation. | Unknown |
| Letter from Neptune Smith, BC Utilities Commission to Derek Griffin stating they have reviewed the mitigation and compensation plan and have no comments. | Unknown |
| Memo from W. Patrick Shera and D.W. Dryden, Ministry of Environment to Derek Griffin regarding the Mitigation and Compensation Plan which requires extensive and substantive revision. | Unknown |
| Fax from Bill Green, Ministry of Environment to Matt Stevens, Aboriginal Relations, BC Hydro recommending re-wording portions of the Mitigation and Compensation Program Plan | Unknown |
| Letter from B.W.R. Eastman, Ministry of Transportation and Highways to Derek Griffin regarding the attached comments from the Regional Bridge Engineer. | Unknown |
| Letter from Denise Mullen-Dalmer of MEMPR to Sophie Pierre of Ktunaxa/Kinbasket Tribal Council regarding thefollow-up to correspondence dated Dec. 20/94 and April 5/95 concerning the review of the EPC Application. | Unknown |
| Letter from Doug Glaum of MSBTC to Derek Griffin of EAO regarding the Archaeology Branch has not identified any potential impacts on archaeological sites or historic trails. | Unknown |
| Email dated Jan 17/07 from Jeff Burrows (Ministry of Environment) to Heather Orr (EAO) regarding the proposed Revelstoke Unit 5 Generation Project | 2007/02/06 |
| Email dated Jan 17/07 from Terri Kinrade (Ministry of Environment) to Heather Orr (EAO) regarding the proposed Revelstoke Unit 5 Generation Project | 2007/02/06 |
| Email dated Jan 16/07 from Cory Legebokow (Ministry of Environment) to Heather Orr (EAO) regarding the proposed Revelstoke Unit 5 Generation Project | 2007/02/06 |
| Email dated Jan 15/07 from Jim Spafford (Ministry of Tourism, Sport and the Arts) to Heather Orr (EAO) regarding the proposed Revelstoke Unit 5 Generation Project | 2007/02/06 |
| Response letter from Minister Cathy McGregor of MELP to John B Holdstock, President of BC Wildlife Federation regarding impacts on fish habitat & populations by the operation | 1997/06/10 |
| Letter from Minister Moe Sihota to John P. Sheehan of BC Hydro with response to Sept. 29/95 letter regarding the approvals and licensing for the various power projects undertaken by BC Hydro. | 1996/02/19 |
| Memo from Denise Mullen-Dalmer of MEMPR to Derek Griffin of EAO regarding MEMPR has no outstanding issues that would prevent certification. | 1995/12/15 |
| Final Project Meeting Notes of July 25, 1996 project meeting | 1995/08/25 |
| Memo from Pat Shera of MELP to Denise Mullen-Dalmer of MEMPR regarding forwarding of review comments received to date (attached). | 1995/07/15 |
| Memo from Pat Shera and Doug Dryden of MELP to Denise Mullen-Dalmer of MEMPR regarding information requirements for MELP's review of the application | 1995/07/15 |
|