Highland Valley Centre for Sustainable Waste Management

Type:Typical EA Process (Active and Complete)Status:Completed / Certified
Category:Waste DisposalPre-application

Start Date:

2005/08/02

Under Review EAO Generated Documents



Folder

Date Posted

Section 24 (4) Order - Time-Limit Extension to October 6, 20082008/09/08
Letter dated April 28/08 from Archie Riddell (EAO) to Mark Freberg (HVC) regarding the lifting of the timeline suspension of the Highland Valley Centre for Sustainable Waste Management Project2008/04/28
Order Under Section 13 Rescinding January 16, 2008 Section 13 Order signed by Archie Riddell (EAO, Project Assessment Director) dated April 22, 2008 2008/04/22
Letter dated April 22/08 from Archie Riddell (EAO) to Mark Freberg (HVC) regarding the Section 13 Order Rescinding the January 16, 2008 Section 13 Order 2008/04/22
Order Under Section 13 Amending Section 11 Order signed by Archie Riddell (EAO, Project Assessment Director) dated January 16, 2008 2008/01/16
Letter dated Jan 16/08 from Archie Riddell (EAO) to Mark Freberg (HVC) granting a Section 13 Order Amending Section 11 Order2008/01/16
Letter dated Dec 7/07 from Archie Riddell (EAO) to Mark Freberg (HVC) suspending the review period to provide opportunity to review addendum and supporting documentation 2007/12/10
Advisory Working Group Meeting Summary dated from Oct 3/07 regarding the proposed Highland Valley Centre for Sustainable Waste Management Project2007/11/01
Letter dated Sept 7/07 from Derek Griffin (EAO) to Mark Freberg (Proponent) regarding confirmed receipt of the HVC Application2007/10/10
Last Updated: 2009-11-07