Hermann Mine Project

Type:Typical EA Process (Active and Complete)Status:Completed / Certified
Category:MiningPre-application

Start Date:

2006/07/06

Under Review EAO Generated Documents



Folder

Date Posted

Letter dated Aug 28/08 from Kathy Eichenberger (EAO) to Kathleen Pomeroy (WCCC) lifting the environmental assessment time limit suspension on the Project2008/08/27
Final notes for the Oct 17/07 Working Group Sub-Committee Meeting in Chetwynd for the proposed Hermann Coal Mine Project. 2008/03/25
Letter dated Nov 16/07 from Bob Hart (EAO) to Kathy Pomeroy (WCCC) regarding consultation with the Halfway River First Nation.2007/11/19
Section 13 Order amending section 11 Order issued on November 15, 2007 by Bob Hart (EAO) for the Hermann Mine Project. 2007/11/16
Final notes for the Apr 3/07 Socio-economic/Community Data Collection and TLUS Approach Meeting for the proposed Hermann Mine Project.2007/09/10
Letter dated Jun 20/07 from Bob Hart (EAO) to Councillor Kori Dokkie and Land Use Manager Bruce Muir (WMFN) in response to June 14, 2007 letter2007/09/10
Letter dated May 17/07 from Bob Hart (EAO) to Councillor Kori Dokkie and Land Use Manager Bruce Muir (WMFN) in response to the March 25 and March 31, 2007 letters2007/08/31
Final notes for the Jul 10/07 Working Group Sub-Committee Meeting in Chetwynd for the proposed Hermann Coal Mine Project.2007/08/31
Letter dated May 15/07 from Bob Hart (EAO) to Chief Chingee (McLeod Lake Indian Band) Re: Proposed Hermann Mine Development Project and Requested Time Limit Suspension2007/08/30
Letter dated May 15/07 from Bob Hart (EAO) to Chief Allan Apsassin (Saulteau First Nations) regarding the Hermann Mine Project and Requested Time Limit Suspension.2007/08/30
Letter dated May 16/07 from Bob Hart (EAO) to Chief Roland Willson (WMFN) in response to the April 20/07 letter and Requested Time Limit Suspension.2007/08/30
Letter dated Jul 13/07 from Bob Hart (EAO) to Kathy Pomeroy (WCCC) temporarily suspending the review of WCCC's Application for an EA Certificate starting Jul 12/07.2007/07/16
Final meeting notes from EAO for the Reclamation and ML/ARD meetings held in Victoria, BC on May 10/07.2007/07/12
Final meeting notes from EAO for the Hermann Coal Mine Project Wildlife - Vegetation meeting held in Fort St. John BC, May 09/07.2007/07/12
Final meeting notes for Apr 17/07 Working Group Meeting for the Hermann Mine Project.2007/06/21
Letter dated Mar 26/07 from Bob Hart (EAO) to Kathleen Pomeroy (WCCC) confirming reciept of WCCC's application for an environmental assessment certificate.2007/03/29
Meeting notes from the Mar 8/07 Working Group teleconference.2007/03/12
Letter dated Feb 1/07 from Bob Hart (EAO) to Kathleen Pomeroy (WCCC) accepting WCCC's application for an EA Certificate for the Hermann Mine Project.2007/02/06
Last Updated: 2009-11-07