Port Alberni Cogeneration Project

Type:Typical EA Process (Active and Complete)Status:Completed / Certified
Category:EnergyPre-application

Start Date:

1999/08/20

Under Review Proponent Comments/Correspondence



Folder

Date Posted

Letter from Proponent to B Claus (Environment Canada) with response to questions raised in October 21, 1999 letter1999/11/23
Letter from Proponent to J McManus (ACRD) with response to ACRD questions regarding Port Alberni Cogeneration Project1999/11/23
Letter from Proponent to S McNaughton (MELP) with responses to MELP's questions regarding the application1999/11/15
Letter from Proponent to M Harano (Tseshaht First Nation) with responses to the issues raised in Harano's letter of Oct. 14/991999/11/15
Letter from Proponent to M Harano (Tseshaht First Nation) with responses to questions raised in Oct. 29/99 letter1999/11/15
Letter from Proponent to D Carter (DFO) with responses to questions raised in Oct. 20/99 letter1999/11/15
Letter from Proponent to B Antcliffe (DFO) with regards to Water Quality on Port Alberni Cogeneration Project1999/11/15
Email from Proponent to K Hardie (EAO) regarding the proponent's position on liabilities is a Tsunami event effects the PAC facility1999/11/02
Letter from Proponent to J Hagen (EAO) with regards to First Nation's consultation for Port Alberni Cogeneration Project1999/10/25
Response letter from Proponent to R McLaughlin (MEI) regarding the October 18, 1999 letter regarding Socio-economic impacts of the proposed project1999/10/25
Letter from N Zorkin (ENKON) on behalf of Proponent to J McManus (ACRD) regarding the impact of water vapour produced by the proposed project1999/10/20
Letter from N Zorkin (Enkon) to J Hagen (EAO) with regards to the Application for a Project Approval Certificate for Port Alberni Cogeneration1999/09/20
Last Updated: 2009-11-21