Cariboo Gold Project

Type:Typical EA Process (Active and Complete)Status:Terminated
Category:MiningPre-application

Start Date:

2000/04/11

Under Review Proponent Comments/Correspondence



Folder

Date Posted

Faxed letter dated Dec 20/02 from Proponent to Marcia Farquhar (EAO) regarding request for amendment of application 2003/01/08
Letter from Frank J. Callaghan (proponent) to Marcia Farquhar (EAO) regarding his awaiting current environmental studies to be received and examined.2001/07/09
Letter from Larry Connell (Env. Manager, Knight Piesold) to Alan Calder. RE: response to July 31 comments regarding revised study terms of reference.2000/08/23
Fish & Aquatic Habitat Baseline Studies Program Report by Knight Piesold Ltd on behalf of the proponent2000/07/20
Letter from Prop. to M Farquhar (EAO) with a request for Timeline Extension in order to explore the extent of the newly discovered Bonanza Ledge zone2000/07/14
Minutes of the Wells Public Liaison Committee Meeting; Thursday June 8 20002000/07/05
Letter from Proponent to M Farquhar (EAO) with comments on the project2000/06/30
Last Updated: 2009-11-21