Radec Forest Solutions Inc. was contracted by Triumph Timber to complete a Routine Effectiveness Evaluation (REE) on project number 6344003; 2005 girdling project on Whalen Lake, Mitchell?s Cove and Farrant Island. See Appendix I Key Map for general locations of the project areas. The contract was designed to complete the review of all project area within one field day. The REE was completed as an overview of the project areas to determine the effectiveness of the treatment and provide any recommendations on further developments.