NOTE:
	    
This information is considered historical as it represents channel 
conditions and configuration at the time of the  survey only.  User 
must accept responsibility of ensuring  that the accuracy  and 
completeness of  provided data is suitable for the needs of the 
project or study.   It is provided "as is" without warranty of any 
kind,  whether express or implied.  Under  no  circumstances will the 
Government of British Columbia be liable  to any person or business 
entity for any   direct,  indirect, special, incidental, consequential, 
or other  damages based on any use of this information.

X/S 3     KOOTENAY RIVER     PROJECT 78-SR-01     OCT 1978
 
POINT    DISTANCE    CHAINAGE   ELEVATION    NO.    REMARKS
 
                         0.00      532.51      0    DUMMY
          2000.00
  515                 2000.00      532.51      1    1997 0+00 X/S 3  
            29.86
13373                 2029.86      539.11      2    MON 330 LB       3  
             1.58
13372                 2031.44      539.20      3    TOP DYKE         3  
             5.91
13371                 2037.35      537.01      4    .                3  
             4.78
13370                 2042.13      535.74      5    TOE              3  
             9.02
13369                 2051.15      534.68      6    .                3  
            10.25
13368                 2061.40      535.25      7    .                3  
             6.49
13367                 2067.89      535.63      8    TOP BANK         3  
             1.16
13366                 2069.05      533.01      9    HWM              3  
             2.35
13365                 2071.40      532.16     10    W/L LB           3  
             7.13
13364                 2078.53      529.91     11    .                3  
             3.11
13363                 2081.63      528.48     12    .                3  
             3.14
13362                 2084.77      526.68     13    .                3  
             3.11
13361                 2087.88      525.64     14    .                3  
             3.11
13360                 2090.99      524.94     15    .                3  
             3.11
13359                 2094.10      524.03     16    .                3  
             3.14
13358                 2097.23      523.60     17    .                3  
             3.11
13357                 2100.34      523.51     18    .                3  
             3.11
13356                 2103.45      523.30     19    .                3  
             3.11
13355                 2106.56      523.02     20    .                3  
             3.14
13354                 2109.69      522.96     21    .                3  
             3.11
13353                 2112.80      522.93     22    .                3  
             3.11
13352                 2115.91      522.90     23    .                3  
             1.55
13351                 2117.46      522.84     24    .                3  
             1.55
13350                 2119.02      522.90     25    .                3  
X/S 3     KOOTENAY RIVER     PROJECT 78-SR-01     OCT 1978
 
POINT    DISTANCE    CHAINAGE   ELEVATION    NO.    REMARKS
 
             3.14
13349                 2122.16      523.18     26    .                3  
             3.11
13348                 2125.26      523.36     27    .                3  
             3.11
13347                 2128.37      523.33     28    .                3  
             3.11
13346                 2131.48      523.11     29    .                3  
             3.11
13345                 2134.59      522.96     30    .                3  
             3.14
13344                 2137.73      522.60     31    .                3  
             3.11
13343                 2140.83      520.59     32    .                3  
             3.11
13342                 2143.94      520.07     33    .                3  
             3.11
13341                 2147.05      520.92     34    .                3  
             3.14
13340                 2150.19      522.20     35    .                3  
             3.11
13339                 2153.29      522.57     36    .                3  
             3.11
13338                 2156.40      522.75     37    .                3  
             3.11
13337                 2159.51      522.84     38    .                3  
             3.14
13336                 2162.65      522.81     39    .                3  
             3.11
13335                 2165.76      522.81     40    .                3  
             3.11
13334                 2168.86      522.90     41    .                3  
             3.11
13333                 2171.97      522.84     42    .                3  
             3.11
13332                 2175.08      522.81     43    .                3  
             3.14
13331                 2178.22      522.60     44    .                3  
             3.11
13330                 2181.32      522.47     45    .                3  
             3.11
13329                 2184.43      522.41     46    .                3  
             3.11
13328                 2187.54      522.54     47    .                3  
             3.14
13327                 2190.68      522.72     48    .                3  
             3.11
13326                 2193.79      522.78     49    .                3  
             3.11
13325                 2196.89      522.81     50    .                3  
             3.11
X/S 3     KOOTENAY RIVER     PROJECT 78-SR-01     OCT 1978
 
POINT    DISTANCE    CHAINAGE   ELEVATION    NO.    REMARKS
 
13324                 2200.00      523.05     51    .                3  
             3.14
13323                 2203.14      523.21     52    .                3  
             3.11
13322                 2206.25      523.30     53    .                3  
             3.11
13321                 2209.36      523.72     54    .                3  
             3.11
13320                 2212.46      523.82     55    .                3  
             3.14
13319                 2215.60      523.88     56    .                3  
             3.11
13318                 2218.71      523.88     57    .                3  
             3.11
13317                 2221.82      523.79     58    .                3  
             3.11
13316                 2224.92      523.91     59    .                3  
             3.26
13315                 2228.18      524.27     60    .                3  
             2.99
13314                 2231.17      524.64     61    .                3  
             3.11
13313                 2234.28      525.34     62    .                3  
             3.11
13312                 2237.39      526.28     63    .                3  
             3.11
13311                 2240.49      527.41     64    .                3  
             3.14
13310                 2243.63      529.00     65    .                3  
             3.11
13309                 2246.74      530.31     66    .                3  
             3.11
13308                 2249.85      531.65     67    .                3  
             1.25
13307                 2251.10      532.05     68    W/L RB           3  
             0.75
13306                 2251.85      533.05     69    HWM              3  
             1.30
13305                 2253.15      534.86     70    .                3  
             2.15
13304                 2255.30      536.10     71    TOP BANK         3  
             2.00
13303                 2257.29      536.33     72    .                3  
             2.45
13302                 2259.74      537.48     73    .                3  
             2.04
13301                 2261.78      537.77     74    MON 329 RB       3  
 
JOIN  515-13301  N 26d55'14" E  261.78