NOTE:
	    
This information is considered historical as it represents channel 
conditions and configuration at the time of the  survey only.  User 
must accept responsibility of ensuring  that the accuracy  and 
completeness of  provided data is suitable for the needs of the 
project or study.   It is provided "as is" without warranty of any 
kind,  whether express or implied.  Under  no  circumstances will the 
Government of British Columbia be liable  to any person or business 
entity for any   direct,  indirect, special, incidental, consequential, 
or other  damages based on any use of this information.

X/S 4     KOOTENAY RIVER     PROJECT 78-SR-01     OCT 1978
 
POINT    DISTANCE    CHAINAGE   ELEVATION    NO.    REMARKS
 
                         0.00      533.92      0    DUMMY
          2000.00
 6808                 2000.00      533.92      1    1986 0+00 X/S 4
            25.32
13489                 2025.32      539.13      2    MON 332 LB       4  
             1.52
13488                 2026.85      539.13      3    TOP DYKE         4  
             4.08
13487                 2030.92      537.49      4    .                4  
             3.84
13486                 2034.76      536.35      5    .                4  
             7.48
13485                 2042.24      535.01      6    .                4  
             5.67
13484                 2047.91      534.18      7    .                4  
             2.71
13483                 2050.62      534.10      8    .                4  
             2.92
13482                 2053.54      533.71      9    .                4  
             7.09
13481                 2060.63      533.90     10    TOP BANK         4  
             0.51
13480                 2061.14      533.20     11    HWM ?            4  
             0.51
13479                 2061.65      532.84     12    .                4  
             1.72
13478                 2063.37      532.36     13    .                4  
             0.44
13477                 2063.81      532.17     14    W/L LB           4  
             0.02
13476                 2063.83      531.99     15    .                4  
             3.05
13475                 2066.87      531.26     16    .                4  
             3.11
13474                 2069.98      530.37     17    .                4  
             3.14
13473                 2073.12      528.39     18    .                4  
             3.11
13472                 2076.23      526.72     19    .                4  
             3.14
13471                 2079.37      525.92     20    .                4  
             3.11
13470                 2082.47      525.10     21    .                4  
             0.94
13469                 2083.42      524.58     22    .                4  
             1.25
13468                 2084.67      524.58     23    .                4  
             0.94
13467                 2085.61      524.83     24    .                4  
             3.14
13466                 2088.75      524.58     25    .                4  
X/S 4     KOOTENAY RIVER     PROJECT 78-SR-01     OCT 1978
 
POINT    DISTANCE    CHAINAGE   ELEVATION    NO.    REMARKS
 
             3.11
13465                 2091.86      523.76     26    .                4  
             3.14
13464                 2095.00      523.30     27    .                4  
             0.91
13463                 2095.91      522.72     28    .                4  
             2.19
13462                 2098.10      522.72     29    .                4  
             3.14
13461                 2101.24      522.81     30    .                4  
             1.25
13460                 2102.49      522.94     31    .                4  
             1.86
13459                 2104.35      522.91     32    .                4  
             3.14
13458                 2107.49      522.45     33    .                4  
             3.11
13457                 2110.59      521.78     34    .                4  
             0.94
13456                 2111.54      521.69     35    .                4  
             2.19
13455                 2113.73      521.63     36    .                4  
             0.61
13454                 2114.34      521.63     37    .                4  
             2.50
13453                 2116.84      522.36     38    .                4  
             3.14
13452                 2119.98      522.69     39    .                4  
             3.11
13451                 2123.09      523.06     40    .                4  
             1.25
13450                 2124.34      523.18     41    .                4  
             1.89
13449                 2126.22      523.06     42    .                4  
             0.94
13448                 2127.17      523.03     43    .                4  
             2.19
13447                 2129.36      523.24     44    .                4  
             3.11
13446                 2132.47      523.61     45    .                4  
             3.14
13445                 2135.61      523.70     46    .                4  
             3.11
13444                 2138.72      523.70     47    .                4  
             3.14
13443                 2141.85      523.85     48    .                4  
             3.11
13442                 2144.96      523.91     49    .                4  
             3.14
13441                 2148.10      523.94     50    .                4  
             3.11
X/S 4     KOOTENAY RIVER     PROJECT 78-SR-01     OCT 1978
 
POINT    DISTANCE    CHAINAGE   ELEVATION    NO.    REMARKS
 
13440                 2151.21      523.94     51    .                4  
             3.14
13439                 2154.35      523.97     52    .                4  
             3.11
13438                 2157.45      523.97     53    .                4  
             3.14
13437                 2160.59      524.22     54    .                4  
             1.55
13436                 2162.15      524.73     55    .                4  
             1.55
13435                 2163.70      524.80     56    .                4  
             3.14
13434                 2166.84      524.83     57    .                4  
             3.11
13433                 2169.95      524.70     58    .                4  
             3.14
13432                 2173.08      524.49     59    .                4  
             3.14
13431                 2176.22      524.49     60    .                4  
             3.11
13430                 2179.33      524.52     61    .                4  
             3.14
13429                 2182.47      524.49     62    .                4  
             3.11
13428                 2185.58      524.52     63    .                4  
             3.14
13427                 2188.71      524.58     64    .                4  
             3.11
13426                 2191.82      524.58     65    .                4  
             3.14
13425                 2194.96      524.40     66    .                4  
             3.11
13424                 2198.07      524.34     67    .                4  
             3.14
13423                 2201.21      524.19     68    .                4  
             3.11
13422                 2204.31      524.34     69    .                4  
             3.14
13421                 2207.45      524.43     70    .                4  
             3.11
13420                 2210.56      524.37     71    .                4  
             3.14
13419                 2213.70      524.31     72    .                4  
             3.14
13418                 2216.84      523.49     73    .                4  
             3.11
13417                 2219.94      524.13     74    .                4  
             3.14
13416                 2223.08      524.09     75    .                4  
             1.55
13415                 2224.64      524.13     76    .                4  
X/S 4     KOOTENAY RIVER     PROJECT 78-SR-01     OCT 1978
 
POINT    DISTANCE    CHAINAGE   ELEVATION    NO.    REMARKS
 
             1.55
13414                 2226.19      524.70     77    .                4  
             3.14
13413                 2229.33      525.74     78    .                4  
             3.11
13412                 2232.44      526.93     79    .                4  
             3.14
13411                 2235.57      528.42     80    .                4  
             3.11
13410                 2238.68      529.95     81    .                4  
             3.14
13409                 2241.82      530.62     82    .                4  
             3.11
13408                 2244.93      531.99     83    .                4  
             0.49
13407                 2245.42      532.20     84    W/L RB           4  
             0.94
13406                 2246.35      532.93     85    HWM              4  
             0.07
13405                 2246.43      534.17     86    .                4  
             0.92
13404                 2247.35      534.65     87    SLUFF            4  
             1.59
13403                 2248.94      536.77     88    .                4  
             1.53
13402                 2250.47      537.34     89    TOP BANK         4  
             4.27
13401                 2254.73      537.63     90    MON 331 RB       4  
 
JOIN  6808-13401  N 29d39'50" E  254.73