The objectives of this project was to replace multiple poorly placed, undersized, fish-movement restricting metal culverts with a clear span bridge structure. The stream name is unknown, and the project site is on the upper plateau of CanFor's TFL 18, west of Clearwater, B.C.
Chris Cole.
Cole, Chris. 2006. Installation of a 12m concrete slab bridge to replace multiple undersized culverts. Forest Investment Account (FIA) - Forest Science Program. Forest Investment Account Report. FIA2006MR104