The objective of this project was to replace the existing ~14 meter slab girder bridge with a 30.48 meter multi- span composite bridge.
Mike Wright and Chris Petersen.
Wright, Michael C., Petersen, Chris. 2007. Palmerston Creek bridge replacement, Eve River Watershed, Coast Forest Region. Forest Investment Account (FIA) - Forest Science Program. Forest Investment Account Report. FIA2007MR185
Topic: FLNRORD Research Program
Keywords: Forest, Investment, Account, (FIA), Bridges, British, Columbia, Design, Construction